BEARING,BALL,1ROW,DEEP GROOVE,6316

Material 4100000129 · BEARING · Plant 1000

AReduceExcess
Material
4100000129
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (121 of 168 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
29 d · P80 32 d
Unit price
Rp 1.7M

Recommendation

  • 1.Forecast 185 EA/year: 176 unplanned (recency-weighted compound poisson (own history)) + 9.3 from the maintenance plan.
  • 2.Lead time ~29 days; expected demand during lead time 14.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 42, order up to 83.
  • 4.Stock 168 exceeds the level to keep (83) by 85.
  • 5.Installed on 168 FuncLoc(s), 121 of them criticality A/B.
  • 6.ML early warning: 100% probability of demand in the next 90 days.
ML early warningLast turnaround used 38Single sourceAbnormal consumptionOpen PO
On hand / on order
168 / 213
next delivery 18 Oct 2026
Today Min / Max
60 / 115
static parameters in BoM
Rec. Min (reorder point)
42
safety stock 29
Rec. Max
83
order qty 41
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.7M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 50 issue days in the last 180 days, last issue 1 days ago, 84 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 13 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (57 units) excluded from the baseline.

Demand pattern Smooth · 181 issue days · 17 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 56.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 168 functional locations

121 with criticality A/B · 229 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_KC-419A
PROPYLENE FAN
A1195.71
PX_KC-247A
SLOP OIL FAN
A194.00
PX_KC-717
FLUSHING OIL COMPRESSOR
A194.00
PX_PP-1776B
RICH AMINE PUMP
A183.62
PX_KT-856A
TURBINE FOR KC-856A
A372.81
PX_PP-103
COOLING WATER PUMP
A472.33
PX_PP-1506
FEED PUMP
A172.76
PX_KC-226
HYDROGEN AIR COMPRESSOR
A162.28
PX_KC-452
HYDROGEN FAN
A162.71
PX_KC-713B
SPENT CAUSTIC FAN
A163.14
PX_KC-732D
METHANOL COMPRESSOR
A163.14
PX_KC-867D
CONDENSATE FAN
A162.71

Lead time and procurement

Lead time 29 ± 15 days (PO history, 47 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
21 Sept 2026PR03
Regular replenishment
154Rp 1.7M18 Oct 2026
open
27 d
17 Sept 2026PR04
Regular (other)
59Rp 1.7M24 Oct 2026
open
37 d
08 Sept 2026PR06
Regular replenishment
86Rp 1.8M29 Sept 202621 d
25 Aug 2026PR03
Regular replenishment
179Rp 1.7M24 Sept 202630 d
19 Aug 2026PR04
Regular (other)
137Rp 1.7M13 Sept 202625 d
18 Aug 2026PR03
Regular replenishment
87Rp 1.8M05 Sept 202618 d
25 Jul 2026PR03
Regular replenishment
133Rp 1.7M24 Aug 202630 d
04 Jun 2026PR03
Regular replenishment
67Rp 1.8M04 Jul 202630 d
13 May 2026PR03
Regular replenishment
167Rp 1.7M01 Jun 202619 d
02 May 2026PR04
Regular (other)
126Rp 1.8M27 May 202625 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72
01 Jan 2027PX_PP-615APump overhaul0.72
09 Jan 2027PX_PP-957APump overhaul0.72
01 Mar 2027PX_PP-807BPump overhaul1.43
02 Mar 2027PX_PP-339APump overhaul0.72
18 Apr 2027PX_PP-481APump overhaul0.72
02 Jun 2027PX_PP-1941APump overhaul0.72
07 Jul 2027PX_KC-505DCompressor major overhaul0.72
02 Aug 2027PX_PP-536Pump overhaul0.72
13 Aug 2027PX_PP-1397Pump overhaul2.15

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_PP-1478B-MPP-1478B-M bearing noise
30 Sept 2026MediumPX_PP-1506Replace bearing PP-1506
30 Sept 2026MediumPX_PP-1892BReplace lamp as per PM finding
29 Sept 2026MediumPX_PP-136BOil leak at PP-136B bearing housing
28 Sept 2026LowPX_KC-886DKC-886D high vibration
28 Sept 2026LowPX_PP-103Oil leak at PP-103 bearing housing
28 Sept 2026MediumPX_PP-1938A[MSI-B-26-ALF-384] Permanent repair
28 Sept 2026HighPY_KC-419AOverhaul
27 Sept 2026MediumPX_PP-807BReplace bearing PP-807B
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
30 Sept 20262201000016264Corrective
30 Sept 20262201000024833Corrective
26 Sept 20262201000004515Corrective
22 Sept 20261204000002989Preventive
21 Sept 20261201000036455Corrective
19 Sept 20261201000003432Corrective
14 Sept 20261201000010974Corrective
10 Sept 20261201000035065Corrective
05 Sept 20262201000000202Corrective
31 Aug 20261203000017844Turnaround
30 Aug 20261203000017844Turnaround
27 Aug 20261201000004902Corrective
25 Aug 20261201000039454Corrective
20 Aug 20261201000003452Corrective
14 Aug 20262201000011746Corrective