Procurement
What must I buy, from whom, by when — and which open POs must I chase?
User role: Buyer / purchasing groupInput: Approved buys from Planner and Maintenance · Output: PR draft → ERP; spend committed → Management
Open POs to expedite
69
Reorder parts whose stock will not last until the open PO arrives
Critical parts with a single supplier
953
Most exposed: KARYA ENERGI SENTOSA PT (67 critical parts, 38% on time)
Suppliers in PR PO history
124
Median on-time rate 39% (PO delivery date on or before the requested date)
1. Purchase requisition draft
Approved buys from the Planner and Maintenance workspaces. PR type, purchasing group and supplier come from each part's own PR PO history; need-by date from the job or the lead time.
No approved buys yet. Approve reorders in the Planner workspace or request job parts in the Maintenance workspace — they land here as PR lines.
2. Expedite open POs
Stock on hand is below expected demand during the lead time, and an open PO is the only cover.
| Part | Crit. | On hand | Demand in lead time | On order | Next delivery | Stockout risk |
|---|---|---|---|---|---|---|
| 4300065132 SEAT RING,VALVE,DWG.262-1832,FOR LCV-124 | B | 0 | 2.32 | 2 | 05 Jan 2027 | 100% |
| 4100080671 BEARING,JOURNAL,SIZE SV126,INCOLOY | A | 1 | 4.06 | 1 | 28 Feb 2027 | 73% |
| 4100082458 BEARING,THRUST PAD,TYPE VJ47,GRAPHITE | A | 1 | 4.16 | 2 | 16 Apr 2027 | 71% |
| 4100084762 SEAL,LABYRINTH,TYPE KI535,A182F11 | A | 0 | 4.18 | 2 | 30 Mar 2027 | 62% |
| 4100077432 BURNER TIP,MODEL PS152,SS316 | A | 0 | 2.02 | 1 | 05 Nov 2026 | 60% |
| 4100005377 SEAL,MECHANICAL,SIZE YV554,SS316 | A | 0 | 1.99 | 1 | 18 Dec 2026 | 59% |
| 4100043505 TRIM SET,CONTROL VALVE,TYPE TZ314,A105 | A | 0 | 1.43 | 1 | 11 Nov 2026 | 58% |
| 4100006884 IMPELLER,SIZE FY592,NBR | A | 0 | 9.74 | 9 | 04 Oct 2026 | 57% |
| 4100050171 SEAT RING,VALVE,TYPE LX216,SS304 | A | 0 | 1.84 | 1 | 08 Oct 2026 | 55% |
| 4100080790 BEARING,JOURNAL,TYPE PE318,MONEL | A | 0 | 1.74 | 1 | 26 Mar 2027 | 52% |
| 4100079959 ANCHOR,REFRACTORY,MODEL KY515,INCOLOY | A | 139 | 235 | 2 | 05 Oct 2026 | 49% |
| 4100048576 POSITIONER,VALVE,TYPE YV85,NBR | A | 1 | 2.67 | 1 | 27 Oct 2026 | 44% |
| 4100082499 BEARING,THRUST PAD,TYPE EB16,CS | A | 1 | 3.49 | 3 | 27 Oct 2026 | 43% |
| 4100043354 TRIM SET,CONTROL VALVE,TYPE FG409,A105 | A | 0 | 2.92 | 3 | 08 Nov 2026 | 37% |
| 4100000788 BEARING,BALL,ANGULAR,NU318BDB | A | 0 | 0.52 | 1 | 24 Oct 2026 | 36% |