BURNER TIP,MODEL PS152,SS316

Material 4100077432 · BURNER TIP · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100077432
Category
BURNER TIP
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 4 FuncLocs A/B)
Supplier
CAHAYA INDUSTRI ABADI PT
Lead time
180 d · P80 204 d
Unit price
Rp 5.4M

Recommendation

  • 1.Forecast 4.1 EA/year: 4.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~180 days; expected demand during lead time 2.0.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 12.
  • 4.On hand 0 + on order 1 is at or below the reorder point: order 11 now.
  • 5.Long lead time: 80% of deliveries took up to 204 days and the fastest seen in its category 79 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
11 EA
Rp 59.9M · order by 01 Oct 2026
Expected arrival ≈ 180 days
Long-leadSingle sourceOpen PO
On hand / on order
0 / 1
next delivery 05 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 6
Rec. Max
12
order qty 4
Service level
100.0%
stockout risk now 60%
Unit price
Rp 5.4M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 69 days ago, 8 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 6.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.

Installed on 4 functional locations

1 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-107
CRACKING FURNACE BF-107
A2239.01
PX_BF-104-BRN02
QO TO QUENCH FITTING
C100.45
PX_BF-105-PD01
CONVECTION SECTION
C100.45
PX_BF-101
CRACKING FURNACE BF-101
S183.02

Lead time and procurement

Lead time 180 ± 68 days (PO history + category, 2 PO lines) · on-time 44%

PR dateTypeQtyUnit priceDeliveryLead time
01 Feb 2026PR06
Regular replenishment
1Rp 5.3M05 Nov 2026
open
277 d
03 Sept 2025PR06
Regular replenishment
1Rp 5.6M02 May 2026241 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026LowPX_BF-107Install scaffolding at BF-107
14 Sept 2026MediumPX_BF-101Replace lamp as per PM finding
08 Sept 2026MediumPX_BF-107Replace lamp as per PM finding
16 Aug 2026MediumPX_BF-101Install scaffolding at BF-101
15 Aug 2026MediumPX_BF-107Hot spot at convection BF-107
08 Aug 2026LowPX_BF-107Cleaning burner BF-107
21 Jul 2026MediumPX_BF-107Replace lamp as per PM finding
21 Jul 2026MediumPX_BF-107Thermograph wall BF-107
18 Jul 2026EmergencyPX_BF-107Hot spot at convection BF-107
10 Jul 2026MediumPX_BF-107Hot spot at convection BF-107

Recent goods issues

Posting dateQtyOrderOrder type
24 Jul 20261201000002081Corrective