BURNER TIP,MODEL PS152,SS316
Material 4100077432 · BURNER TIP · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100077432
- Category
- BURNER TIP
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (1 of 4 FuncLocs A/B)
- Supplier
- CAHAYA INDUSTRI ABADI PT
- Lead time
- 180 d · P80 204 d
- Unit price
- Rp 5.4M
Recommendation
- 1.Forecast 4.1 EA/year: 4.1 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~180 days; expected demand during lead time 2.0.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 12.
- 4.On hand 0 + on order 1 is at or below the reorder point: order 11 now.
- 5.Long lead time: 80% of deliveries took up to 204 days and the fastest seen in its category 79 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
11 EA
Rp 59.9M · order by 01 Oct 2026
Expected arrival ≈ 180 days
Long-leadSingle sourceOpen PO
On hand / on order
0 / 1
next delivery 05 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 6
Rec. Max
12
order qty 4
Service level
100.0%
stockout risk now 60%
Unit price
Rp 5.4M
PO history
ML early warning: 4% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 69 days ago, 8 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 6.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~79 days.
Installed on 4 functional locations
1 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-107 CRACKING FURNACE BF-107 | A | 2 | 23 | 9.01 |
| PX_BF-104-BRN02 QO TO QUENCH FITTING | C | 1 | 0 | 0.45 |
| PX_BF-105-PD01 CONVECTION SECTION | C | 1 | 0 | 0.45 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 1 | 8 | 3.02 |
Lead time and procurement
Lead time 180 ± 68 days (PO history + category, 2 PO lines) · on-time 44%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 01 Feb 2026 | PR06 Regular replenishment | 1 | Rp 5.3M | 05 Nov 2026 open | 277 d |
| 03 Sept 2025 | PR06 Regular replenishment | 1 | Rp 5.6M | 02 May 2026 | 241 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Sept 2026 | Low | PX_BF-107 | Install scaffolding at BF-107 |
| 14 Sept 2026 | Medium | PX_BF-101 | Replace lamp as per PM finding |
| 08 Sept 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 16 Aug 2026 | Medium | PX_BF-101 | Install scaffolding at BF-101 |
| 15 Aug 2026 | Medium | PX_BF-107 | Hot spot at convection BF-107 |
| 08 Aug 2026 | Low | PX_BF-107 | Cleaning burner BF-107 |
| 21 Jul 2026 | Medium | PX_BF-107 | Replace lamp as per PM finding |
| 21 Jul 2026 | Medium | PX_BF-107 | Thermograph wall BF-107 |
| 18 Jul 2026 | Emergency | PX_BF-107 | Hot spot at convection BF-107 |
| 10 Jul 2026 | Medium | PX_BF-107 | Hot spot at convection BF-107 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 24 Jul 2026 | 1 | 201000002081 | Corrective |