Maintenance & Reliability

Will the parts for my planned jobs be there, and which critical parts are unprotected?

User role: Maintenance planner / reliability engineerInput: Maintenance plan, failure history, demand forecast · Output: Part requests → Procurement
Part-consuming jobs, next 90 days
88
43 ready · 3 covered by open PO
Jobs with missing parts
42
109 parts short
ML early warnings
46
Likely needed within 90 days, no stock and no PO
Unprotected never-used parts
862
830 of them criticality A/B · no stock, insurance review

1. Job readiness — next 90 days

Stock is allocated to jobs in due-date order; an open PO counts only if it arrives before the job. Parts per job come from the BoM of the job's FuncLoc.

DueEquipmentJobPartsStatus
01 Oct 2026PX_KC-373B
CONDENSATE BLOWER · crit. S
Filter element replacement
4100086235 need 1 · short 1
4100086359 need 1
Short
01 Oct 2026PX_PP-1157-M
MOTOR FOR PP-1157 · crit. A
Re-greasing Bearing Motor
4100092269 need 2,149 · short 2,147
Short
01 Oct 2026PX_PP-1583A
CAUSTIC PUMP · crit. B
Pump overhaul
4300016217 need 1 · short 1
4100010788 need 1
4100012299 need 1 · short 1
+4 more
Short
01 Oct 2026PX_PP-1720D
METHANOL PUMP · crit. C
Lube oil change
4100108685 need 1 · short 1
Short
01 Oct 2026PX_TCV-1974
HE-1967C TEMP CONTROL · crit. B
Final Element Overhaul; CV
4300063135 need 1
4100044101 need 1 · short 1
4300063187 need 1 · short 1
+2 more
Short
01 Oct 2026PX_TCV-918
TEMPERATURE CONTROL VALVE · crit. C
Final Element Overhaul; CV
4300035851 need 1 · short 1
4300035889 need 1 · short 1
Short
01 Oct 2026PY_PP-1584B
COOLING WATER PUMP · crit. B
Pump overhaul
4100005164 need 1
4300059410 need 1 · short 1
4300059420 need 3 · short 3
+6 more
Short
02 Oct 2026PX_TCV-427
KC-448D TEMP CONTROL · crit. B
Final Element Overhaul; CV
4100014098 need 1 · short 1
Short
30 Oct 2026PX_PP-1063
C4 PRODUCT PUMP · crit. A
Lube oil change
4100108685 need 1 · short 1
4100107144 need 1
Short
31 Oct 2026PX_PP-1177-M
MOTOR FOR PP-1177 · crit. C
Re-greasing Bearing Motor
4100091893 need 18 · short 13
Short
31 Oct 2026PX_PP-588
DILUTION STEAM PUMP · crit. A
Lube oil change
4100107381 need 1 · short 1
Short
01 Nov 2026PX_KC-235D
DEMIN WATER FAN · crit. A
Compressor major overhaul
4100001194 need 1
4100014049 need 1
4100084466 need 1
+22 more
Short

Request the missing parts

MaterialNeeded for jobsShortFirst job dueJobsRequest qtyDecision
A4100086235
FILTER ELEMENT,SEAL GAS,3MICRON,P/N FE-8
3 EA301 Oct 20263
A4100092269
GREASE,LITHIUM,NLGI 3,1KG
2,149 KG2,14701 Oct 20261
B4300016217
SLEEVE,SHAFT,DWG.906-3135,FOR PP-1583A
1 EA101 Oct 20261
A4100012299
RING,WEAR,TYPE II531,MONEL
1 EA101 Oct 20261
B4300016250
IMPELLER,DWG.248-4317,FOR PP-1583A
1 EA101 Oct 20261
B4100009153
SLEEVE,SHAFT,SIZE QH752,A105
1 EA101 Oct 20261
A4100005111
SEAL,MECHANICAL,SIZE FS410,VITON
2 SET201 Oct 20262
A4100108685
OIL,LUBRICANT,ISO VG 32,MINERAL,1L
2 L201 Oct 20262
B4100044101
TRIM SET,CONTROL VALVE,TYPE YV294,GRAPHI
1 SET101 Oct 20261
B4300063187
SEAT RING,VALVE,DWG.639-1755,FOR TCV-197
1 EA101 Oct 20261
B4300063224
TRIM SET,CONTROL VALVE,DWG.335-6490,FOR
1 SET101 Oct 20261
C4300035851
TRIM SET,CONTROL VALVE,DWG.481-3301,FOR
1 SET101 Oct 20261
1–12 of 109

2. Next turnaround readiness

Assumes the next turnaround repeats the scope of the last one, detected in the data as 01 Nov 2025 – 31 Jan 2026 (360 parts, 145,095 units on turnaround orders; 36% of all units issued in 17 months). Stock on the day = on hand + open POs arriving before it + identical stock − expected routine and planned use until then. Order-by = start date − the lead time 80% of past deliveries met.

Turnaround readiness
58%
208 of 360 parts covered on 01 Apr 2027
Parts short
152
139 critical (A/B)
Too late to order normally
15
Order-by date already passed: expedite or re-plan
Value to buy
Rp 7.0B
Shortfall × unit price
MaterialLast TAM usedAvailable on the dayShortOrder byValueRequest qtyDecision
A4100006884ExpediteNeeds sign-off
IMPELLER,SIZE FY592,NBR
5 EA0528 Jul 2026Rp 1.1B
A4100080671Expedite
BEARING,JOURNAL,SIZE SV126,INCOLOY
1 SET0128 May 2026Rp 597.5M
A4100043354Expedite
TRIM SET,CONTROL VALVE,TYPE FG409,A105
1 SET0111 Jul 2026Rp 189.6M
A4100080619Expedite
BEARING,JOURNAL,SIZE MG906,GRAPHITE
2 SET1.14126 Jul 2026Rp 130.2M
A4300008489Expedite
SEAL,LABYRINTH,DWG.662-8839,FOR KC-391D
1 SET0.97131 Aug 2026Rp 117.8M
A4100084466Expedite
SEAL,LABYRINTH,SIZE CH566,CS
1 SET0131 Aug 2026Rp 94.6M
A4300008344Expedite
SEAL,LABYRINTH,DWG.381-1020,FOR KC-391D
1 SET0.97131 Aug 2026Rp 56.7M
A4100046807Expedite
DIAPHRAGM,ACTUATOR,MODEL LB982,VITON
2 EA0222 Sept 2026Rp 26.7M
A4100050348Expedite
SEAT RING,VALVE,SIZE LY983,VITON
2 EA0229 Sept 2026Rp 22.6M
A4100047179Expedite
DIAPHRAGM,ACTUATOR,SIZE NX745,A105
9 EA3.94622 Sept 2026Rp 18.7M
A4100046840Expedite
DIAPHRAGM,ACTUATOR,TYPE VP55,CS
1 EA0122 Sept 2026Rp 4.4M
A4100046941Expedite
DIAPHRAGM,ACTUATOR,TYPE QT820,NBR
1 EA0122 Sept 2026Rp 4.4M
1–12 of 152

3. ML early warnings

Gradient-boosting model: probability that the part is needed in the next 90 days. Shown when ≥ 30% and nothing is on hand or on order (on the hold-out, parts scored ≥ 30% were needed 74% of the time vs 7.1% on average).

MaterialP(needed, 90 d)Typical issueLead timeLast issuedRequest qtyDecision
A4100098110
SCREW,TAPPING,M6X20MM,CS ZN
100%14816 d30 Sept 2026
A4100075392Long-lead
CERAMIC FIBER,BLANKET,25T,96KG/M3,1430C
100%1.3867 d27 Sept 2026
A4100029734
ELBOW,45DEG,1/2IN,SCH40,SS316,BW
99%4.3820 d30 Sept 2026
A4100019476SCE
O-RING,VITON,7MM ID,3.5MM CS
99%2.6525 d25 Sept 2026
A4100098225
SCREW,TAPPING,M6X16MM,SS304
98%9320 d27 Jul 2026
C4100101773
ANTIRUST,SPRAY TYPE,350ML/CAN,TYPE-B
98%2.6518 d20 Sept 2026
A4100029750
ELBOW,45DEG,1/4IN,SCH40,A234WPB,SW
98%3.5330 d26 Sept 2026
A4100073634Long-lead
CASTABLE,REFRACTORY,LW,1300DEG C
97%46.568 d10 Sept 2026
A4100075550
CERAMIC FIBER,BLANKET,50T,96KG/M3,1430C
93%1.356 d15 Sept 2026
A4100032969
FLANGE,SO,3/4IN,300#,SS316,RF
92%4.335 d27 Sept 2026
S4100098240
SCREW,TAPPING,M3X16MM,CS ZN
92%11015 d08 Aug 2026
A4100014256SCE
GASKET,SW,3/4IN,300#,GRAPHITE
91%3.2949 d28 Jul 2026
1–12 of 46

4. Insurance spare review

Parts never issued in 17 months and not in stock, critical (A/B) first. Their demand comes from the failure rate of the equipment they sit on; the cost model says holding the reorder-point level is cheaper than the downtime risk. Confirm before buying. Safety-critical (SCE) parts are not reviewed here: they always keep a spare, so their gaps (202) are already Planner reorders.

MaterialCritical FuncLocsExpected demand / yrLead timeUnit priceKeep qtyDecision
A4100079413
ANCHOR,REFRACTORY,TYPE VU651,INCOLOY
374968 dRp 41,974
A4100071894
FIREBRICK,INSUL,28,65T,114W,230L
167376 dRp 157,612
A4100072283
FIREBRICK,INSUL,23,65T,114W,230L
161776 dRp 157,612
A4100079382
ANCHOR,REFRACTORY,SIZE UQ491,MONEL
161468 dRp 41,974
A4100072013
FIREBRICK,INSUL,26,65T,114W,230L
252076 dRp 157,612
A4100080594
ANCHOR,REFRACTORY,SIZE VD157,MONEL
144268 dRp 41,974
A4100079222
ANCHOR,REFRACTORY,SIZE WI871,A182F11
342468 dRp 41,974
A4100079718
ANCHOR,REFRACTORY,SIZE JU805,SS316
141168 dRp 41,974
A4100079183
ANCHOR,REFRACTORY,MODEL CS21,GRAPHITE
141168 dRp 41,974
A4100074380
CASTABLE,REFRACTORY,LW,1700DEG C
321158 dRp 43,840
A4100075152
CASTABLE,REFRACTORY,LW,1600DEG C
220658 dRp 43,840
A4100079092
ANCHOR,REFRACTORY,TYPE IN916,GRAPHITE
116668 dRp 41,974
1–12 of 400