O-RING,VITON,7MM ID,3.5MM CS
Material 4100019476 · O-RING · Plant 1000
ASafety-criticalReorderCriticalStockout
- Material
- 4100019476
- Category
- O-RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (14 of 22 FuncLocs A/B, 4 safety/shutdown valve)
- Supplier
- CAHAYA TEKNIK PERSADA PT
- Lead time
- 25 d · P80 28 d
- Unit price
- Rp 164,113
Recommendation
- 1.Safety-critical element: installed on 4 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 53 EA/year: 50 unplanned (recency-weighted compound poisson (own history)) + 3.6 from the maintenance plan.
- 3.Lead time ~25 days; expected demand during lead time 3.4.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 16, order up to 70.
- 5.On hand 0 + on order 0 is at or below the reorder point: order 70 now.
- 6.Installed on 22 FuncLoc(s), 14 of them criticality A/B.
- 7.ML early warning: 99% probability of demand in the next 90 days.
Proposed purchase requisition
70 EA
Rp 11.5M · order by 01 Oct 2026
Expected arrival ≈ 25 days
Safety-critical (SCE)ML early warningLast turnaround used 34Single sourceAbnormal consumption
On hand / on order
0 / 0
no open PO
Today Min / Max
14 / 35
static parameters in BoM
Rec. Min (reorder point)
16
safety stock 13
Rec. Max
70
order qty 54
Service level
100.0%
stockout risk now 72%
Unit price
Rp 164,113
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 6 days ago, 9 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (36 units) excluded from the baseline.
Demand pattern Smooth · 31 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 5.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.
Installed on 22 functional locations
14 with criticality A/B · 28 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-308B REFLUX BLOWER | A | 1 | 6 | 2.28 |
| PX_KT-419A TURBINE FOR KC-419A | A | 4 | 6 | 2.81 |
| PX_KC-317B RICH AMINE FAN | A | 1 | 4 | 1.85 |
| PY_PP-1183A BFW PUMP | A | 4 | 4 | 1.47 |
| PX_KC-476C ETHYLENE FAN | A | 1 | 0 | 0.57 |
| PX_KC-669 DEMIN WATER BLOWER | A | 1 | 0 | 0.57 |
| PX_KC-930C SLOP OIL FAN | A | 1 | 0 | 0.57 |
| PX_PP-479 SEAL OIL PUMP | B | 1 | 10 | 2.76 |
| PX_KC-853D SLOP OIL COMPRESSOR | B | 1 | 4 | 1.85 |
| PX_PP-1782B LUBE OIL PUMP | B | 1 | 1 | 0.19 |
| PX_PP-1748 REFLUX PUMP | B | 1 | 0 | 0.19 |
| PX_SDV-1467A VD-1378 SHUTDOWN VALVE | B | 1 | 0 | 0.06 |
Lead time and procurement
Lead time 25 ± 12 days (PO history, 9 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 14 Apr 2026 | PR03 Regular replenishment | 46 | Rp 161,471 | 11 May 2026 | 27 d |
| 14 Apr 2026 | PR04 Regular (other) | 35 | Rp 167,277 | 11 May 2026 | 27 d |
| 12 Apr 2026 | PR06 Regular replenishment | 17 | Rp 163,239 | 11 May 2026 | 29 d |
| 12 Mar 2026 | PR03 Regular replenishment | 51 | Rp 168,649 | 04 Apr 2026 | 23 d |
| 26 Feb 2026 | PR03 Regular replenishment | 54 | Rp 163,680 | 10 Mar 2026 | 12 d |
| 05 Aug 2025 | PR06 Regular replenishment | 41 | Rp 165,354 | 13 Aug 2025 | 8 d |
| 04 Aug 2025 | PR01 Import / long-lead | 57 | Rp 164,632 | 31 Aug 2025 | 27 d |
| 20 May 2025 | PR03 Regular replenishment | 42 | Rp 156,353 | 08 Jun 2025 | 19 d |
| 14 May 2025 | PR06 Regular replenishment | 44 | Rp 164,113 | 25 Jun 2025 | 42 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Mar 2027 | PY_PP-1183A | Pump overhaul | 2.86 |
| 02 Aug 2027 | PX_PP-536 | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 12 Sept 2026 | Medium | PX_PP-479 | Install scaffolding at PP-479 |
| 06 Sept 2026 | Medium | PX_KC-308B | Install scaffolding at KC-308B |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 01 Sept 2026 | High | PX_KC-582B | KC-582B high vibration |
| 27 Aug 2026 | Medium | PY_PP-1183A | Replace lamp as per PM finding |
| 26 Aug 2026 | Low | PX_KC-582B | Painting KC-582B |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 25 Sept 2026 | 2 | 201000018567 | Corrective |
| 22 Sept 2026 | 3 | 201000019618 | Corrective |
| 20 Aug 2026 | 1 | 201000025413 | Corrective |
| 08 Aug 2026 | 1 | 201000036904 | Corrective |
| 30 Jun 2026 | 1 | 201000006875 | Corrective |
| 03 May 2026 | 4 | 201000006586 | Corrective |
| 20 Mar 2026 | 10 | 201000005983 | Corrective |
| 24 Feb 2026 | 3 | 201000009373 | Corrective |
| 23 Feb 2026 | 5 | 201000005996 | Corrective |
| 17 Feb 2026 | 2 | 201000011012 | Corrective |
| 06 Feb 2026 | 2 | 203000032991 | Turnaround |
| 22 Jan 2026 | 4 | 201000025810 | Corrective |
| 19 Jan 2026 | 3 | 201000030708 | Corrective |
| 28 Dec 2025 | 10 | 203000006078 | Turnaround |
| 13 Dec 2025 | 1 | 201000012763 | Corrective |