O-RING,VITON,7MM ID,3.5MM CS

Material 4100019476 · O-RING · Plant 1000

ASafety-criticalReorderCriticalStockout
Material
4100019476
Category
O-RING
Base unit
EA
MRP type
Stock Item
Criticality
A (14 of 22 FuncLocs A/B, 4 safety/shutdown valve)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
25 d · P80 28 d
Unit price
Rp 164,113

Recommendation

  • 1.Safety-critical element: installed on 4 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 53 EA/year: 50 unplanned (recency-weighted compound poisson (own history)) + 3.6 from the maintenance plan.
  • 3.Lead time ~25 days; expected demand during lead time 3.4.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 16, order up to 70.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 70 now.
  • 6.Installed on 22 FuncLoc(s), 14 of them criticality A/B.
  • 7.ML early warning: 99% probability of demand in the next 90 days.
Proposed purchase requisition
70 EA
Rp 11.5M · order by 01 Oct 2026
Expected arrival ≈ 25 days
Safety-critical (SCE)ML early warningLast turnaround used 34Single sourceAbnormal consumption
On hand / on order
0 / 0
no open PO
Today Min / Max
14 / 35
static parameters in BoM
Rec. Min (reorder point)
16
safety stock 13
Rec. Max
70
order qty 54
Service level
100.0%
stockout risk now 72%
Unit price
Rp 164,113
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 6 days ago, 9 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (36 units) excluded from the baseline.

Demand pattern Smooth · 31 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 5.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~14 days.

Installed on 22 functional locations

14 with criticality A/B · 28 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-308B
REFLUX BLOWER
A162.28
PX_KT-419A
TURBINE FOR KC-419A
A462.81
PX_KC-317B
RICH AMINE FAN
A141.85
PY_PP-1183A
BFW PUMP
A441.47
PX_KC-476C
ETHYLENE FAN
A100.57
PX_KC-669
DEMIN WATER BLOWER
A100.57
PX_KC-930C
SLOP OIL FAN
A100.57
PX_PP-479
SEAL OIL PUMP
B1102.76
PX_KC-853D
SLOP OIL COMPRESSOR
B141.85
PX_PP-1782B
LUBE OIL PUMP
B110.19
PX_PP-1748
REFLUX PUMP
B100.19
PX_SDV-1467A
VD-1378 SHUTDOWN VALVE
B100.06

Lead time and procurement

Lead time 25 ± 12 days (PO history, 9 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
14 Apr 2026PR03
Regular replenishment
46Rp 161,47111 May 202627 d
14 Apr 2026PR04
Regular (other)
35Rp 167,27711 May 202627 d
12 Apr 2026PR06
Regular replenishment
17Rp 163,23911 May 202629 d
12 Mar 2026PR03
Regular replenishment
51Rp 168,64904 Apr 202623 d
26 Feb 2026PR03
Regular replenishment
54Rp 163,68010 Mar 202612 d
05 Aug 2025PR06
Regular replenishment
41Rp 165,35413 Aug 20258 d
04 Aug 2025PR01
Import / long-lead
57Rp 164,63231 Aug 202527 d
20 May 2025PR03
Regular replenishment
42Rp 156,35308 Jun 202519 d
14 May 2025PR06
Regular replenishment
44Rp 164,11325 Jun 202542 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Mar 2027PY_PP-1183APump overhaul2.86
02 Aug 2027PX_PP-536Pump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
12 Sept 2026MediumPX_PP-479Install scaffolding at PP-479
06 Sept 2026MediumPX_KC-308BInstall scaffolding at KC-308B
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
01 Sept 2026HighPX_KC-582BKC-582B high vibration
27 Aug 2026MediumPY_PP-1183AReplace lamp as per PM finding
26 Aug 2026LowPX_KC-582BPainting KC-582B
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
19 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A

Recent goods issues

Posting dateQtyOrderOrder type
25 Sept 20262201000018567Corrective
22 Sept 20263201000019618Corrective
20 Aug 20261201000025413Corrective
08 Aug 20261201000036904Corrective
30 Jun 20261201000006875Corrective
03 May 20264201000006586Corrective
20 Mar 202610201000005983Corrective
24 Feb 20263201000009373Corrective
23 Feb 20265201000005996Corrective
17 Feb 20262201000011012Corrective
06 Feb 20262203000032991Turnaround
22 Jan 20264201000025810Corrective
19 Jan 20263201000030708Corrective
28 Dec 202510203000006078Turnaround
13 Dec 20251201000012763Corrective