DIAPHRAGM,ACTUATOR,SIZE NX745,A105
Material 4100047179 · DIAPHRAGM · Plant 1000
ALong-leadMonitorTAM reserve
- Material
- 4100047179
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (5 of 9 FuncLocs A/B)
- Supplier
- TIRTA SEJAHTERA PERSADA PT
- Lead time
- 144 d · P80 191 d
- Unit price
- Rp 3.1M
Recommendation
- 1.Forecast 0.1 EA/year: 0.1 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~144 days; expected demand during lead time 0.0.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
- 4.Used only during the last turnaround (9 EA): keep it for the next one instead of treating it as slow-moving.
- 5.Long lead time: 80% of deliveries took up to 191 days and the fastest seen in its category 46 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 9 FuncLoc(s), 5 of them criticality A/B.
Long-leadLast turnaround used 9Single source
On hand / on order
4 / 0
no open PO
Today Min / Max
2 / 4
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.9%
stockout risk now 0%
Unit price
Rp 3.1M
PO history
ML early warning: 22% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (9 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 121.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~46 days.
Installed on 9 functional locations
5 with criticality A/B · 9 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PCV-1466B BY PASS DUCT | A | 1 | 2 | 0.51 |
| PX_LCV-1990 PP-1498C LEVEL CONTROL | A | 1 | 0 | 0.12 |
| PX_PCV-1166 PRESSURE CONTROL VALVE | A | 1 | 0 | 0.08 |
| PX_PCV-984 KC-984C PRESSURE CONTROL | A | 1 | 0 | 0.08 |
| PX_FCV-1980A PP-1810A OUTLET FLOW | B | 1 | 3 | 0.96 |
| PX_PCV-372 PRESSURE CONTROL VALVE | C | 1 | 3 | 0.94 |
| PX_FCV-1474 VD-444B OUTLET FLOW | C | 1 | 0 | 0.11 |
| PX_LCV-1376 LEVEL CONTROL VALVE | C | 1 | 0 | 0.12 |
| PX_LCV-637 LEVEL CONTROL VALVE | C | 1 | 0 | 0.12 |
Lead time and procurement
Lead time 144 ± 82 days (PO history + category, 2 PO lines) · on-time 35%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 27 Oct 2025 | PR03 Regular replenishment | 2 | Rp 3.0M | 03 Mar 2026 | 127 d |
| 29 Jun 2025 | PR06 Regular replenishment | 4 | Rp 3.2M | 07 Jan 2026 | 192 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 04 Sept 2026 | Low | PX_PCV-1466B | PCV-1466B; valve hunting |
| 29 May 2026 | Low | PX_PCV-372 | PCV-372 passing |
| 15 Mar 2026 | Medium | PX_FCV-1980A | Repair insulation FCV-1980A |
| 08 Feb 2026 | Low | PX_PCV-372 | PCV-372; valve hunting |
| 31 Aug 2025 | Low | PX_FCV-1980A | FCV-1980A; small leak at packing |
| 23 May 2025 | Low | PX_PCV-1466B | Replace lamp as per PM finding |
| 15 May 2025 | Medium | PX_PCV-372 | PSM25/Overhaul PCV-372 |
| 08 May 2025 | Low | PX_FCV-1980A | FCV-1980A; small leak at packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 23 Nov 2025 | 3 | 203000038363 | Turnaround |
| 22 Nov 2025 | 3 | 203000038363 | Turnaround |
| 18 Nov 2025 | 1 | 203000038363 | Turnaround |
| 18 Nov 2025 | 2 | 203000038363 | Turnaround |