GASKET,RING,4IN,300#,GRAPHITE

Material 4100014098 · GASKET · Plant 1000

ASafety-criticalMonitorStockout
Material
4100014098
Category
GASKET
Base unit
EA
MRP type
Stock Item
Criticality
A (44 of 69 FuncLocs A/B, 4 safety/shutdown valve)
Supplier
BINTANG PERKASA ABADI PT
Lead time
44 d · P80 73 d
Unit price
Rp 245,611

Recommendation

  • 1.Safety-critical element: installed on 4 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 117 EA/year: 113 unplanned (recency-weighted compound poisson (own history)) + 4.3 from the maintenance plan.
  • 3.Lead time ~44 days; expected demand during lead time 15 (incl. 1.4 planned).
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 57, order up to 142.
  • 5.Installed on 69 FuncLoc(s), 44 of them criticality A/B.
  • 6.ML early warning: 100% probability of demand in the next 90 days.
Safety-critical (SCE)ML early warningLast turnaround used 42Single sourceAbnormal consumptionOpen POPlanned demand in lead time
On hand / on order
0 / 140
next delivery 18 Oct 2026
Today Min / Max
189 / 526
static parameters in BoM
Rec. Min (reorder point)
57
safety stock 42
Rec. Max
142
order qty 85
Service level
99.9%
stockout risk now 0%
Unit price
Rp 245,611
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 11 issue days in the last 180 days, last issue 14 days ago, 39 failure notifications on its equipment in 90 days, 3 planned jobs in 90 days, 8 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (44 units) excluded from the baseline.

Demand pattern Smooth · 40 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 8.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 69 functional locations

44 with criticality A/B · 87 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-103
CRACKING FURNACE BF-103
A13814.58
PX_BF-111
CRACKING FURNACE BF-111
A1239.01
PX_KC-717
FLUSHING OIL COMPRESSOR
A194.00
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_PP-818
LUBE OIL PUMP
A161.90
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_CL-1839
COOLING WATER COLUMN
A131.23
PX_KC-396
WASH WATER BLOWER
A131.43
PX_HE-621
BOTTOM REBOILER
A120.22
PX_KC-137A
C4 PRODUCT COMPRESSOR
A121.43
PX_KC-464A
CONDENSATE BLOWER
A121.43
PX_KT-460B
TURBINE FOR KC-460B
A121.96

Lead time and procurement

Lead time 44 ± 29 days (PO history, 19 PO lines) · on-time 45%

PR dateTypeQtyUnit priceDeliveryLead time
11 Sept 2026PR05
Project / turnaround
81Rp 243,72506 Jan 2027
open
117 d
19 Aug 2026PR06
Regular replenishment
38Rp 253,34415 Sept 202627 d
08 Aug 2026PR03
Regular replenishment
59Rp 248,61618 Oct 2026
open
71 d
13 Jun 2026PR03
Regular replenishment
81Rp 239,84417 Aug 202665 d
20 May 2026PR04
Regular (other)
92Rp 238,69920 Jul 202661 d
12 May 2026PR03
Regular replenishment
86Rp 243,74926 May 202614 d
24 Apr 2026PR01
Import / long-lead
95Rp 245,35317 Jul 202684 d
16 Apr 2026PR03
Regular replenishment
62Rp 253,92906 May 202620 d
29 Mar 2026PR04
Regular (other)
111Rp 241,30912 Jun 202675 d
29 Mar 2026PR06
Regular replenishment
49Rp 249,82909 Apr 202611 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Oct 2026PX_TCV-427Final Element Overhaul; CV0.72
24 Oct 2026PX_LCV-1730CFinal Element Overhaul; Control Valve0.72
26 Dec 2026PX_KT-264ATurbine major overhaul0.72
01 Feb 2027PX_FCV-1732Final Element Overhaul; Control Valve0.72
12 Aug 2027PY_LCV-375Final Element Overhaul; CV0.72
13 Aug 2027PX_PP-1397Pump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
29 Sept 2026MediumPX_KC-575BInstall scaffolding at KC-575B
26 Sept 2026MediumPX_KC-365CKC-365C lube oil filter DP high
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding
24 Sept 2026EmergencyPX_KC-538KC-538 high vibration
22 Sept 2026MediumPX_BF-111Install cover plate BF-111
21 Sept 2026LowPX_KC-717Leak from packing
20 Sept 2026MediumPX_BF-103Leak from packing
19 Sept 2026LowPX_BF-103Leak from packing
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair

Recent goods issues

Posting dateQtyOrderOrder type
17 Sept 20264209000036917Other maintenance
16 Sept 20261201000037563Corrective
02 Sept 20263201000014482Corrective
02 Sept 20261201000014482Corrective
26 Aug 20265201000022159Corrective
03 Aug 20262201000035128Corrective
14 Jul 20263201000028281Corrective
29 Jun 20264201000010419Corrective
10 Jun 202610209000014321Other maintenance
06 Jun 20267204000030837Preventive
14 May 20261201000025335Corrective
24 Apr 20264201000020979Corrective
27 Mar 20261204000036669Preventive
14 Mar 20261201000029505Corrective
13 Mar 20262201000025388Corrective