OIL,LUBRICANT,ISO VG 100,SYNTHETIC,5L
Material 4100107144 · OIL · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100107144
- Category
- OIL
- Base unit
- L
- MRP type
- Stock Item
- Criticality
- A (8 of 10 FuncLocs A/B)
- Supplier
- DUTA ENERGI ABADI PT
- Lead time
- 20 d · P80 25 d
- Unit price
- Rp 224,930
Recommendation
- 1.Forecast 103 L/year: 101 unplanned (recency-weighted compound poisson (own history)) + 2.1 from the maintenance plan.
- 2.Lead time ~20 days; expected demand during lead time 5.6.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 44, order up to 127.
- 4.On hand 8 + on order 0 is at or below the reorder point: order 119 now.
- 5.Installed on 10 FuncLoc(s), 8 of them criticality A/B.
- 6.ML early warning: 95% probability of demand in the next 90 days.
Proposed purchase requisition
119 L
Rp 26.8M · order by 01 Oct 2026
Expected arrival ≈ 20 days
ML early warningLast turnaround used 14Single sourceAbnormal consumption
On hand / on order
8 / 0
no open PO
Today Min / Max
20 / 56
static parameters in BoM
Rec. Min (reorder point)
44
safety stock 39
Rec. Max
127
order qty 83
Service level
100.0%
stockout risk now 40%
Unit price
Rp 224,930
PO history
ML early warning: 95% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 53 days ago, 6 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (18 units) excluded from the baseline.
Demand pattern Lumpy · 15 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~13 days.
Installed on 10 functional locations
8 with criticality A/B · 10 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-226 HYDROGEN AIR COMPRESSOR | A | 1 | 6 | 2.28 |
| PX_KC-752A CONDENSATE BLOWER | A | 1 | 4 | 1.85 |
| PX_KC-671D FEED BLOWER | A | 1 | 3 | 1.00 |
| PX_KC-137A C4 PRODUCT COMPRESSOR | A | 1 | 2 | 1.43 |
| PX_PP-1801A DEMIN WATER PUMP | A | 1 | 1 | 0.19 |
| PY_KC-636C SLOP OIL COMPRESSOR | A | 1 | 1 | 0.57 |
| PX_PP-1063 C4 PRODUCT PUMP | A | 1 | 0 | 0.19 |
| PX_PP-1583A CAUSTIC PUMP | B | 1 | 2 | 0.62 |
| PX_KC-365C INHIBITOR BLOWER | S | 1 | 7 | 3.14 |
| PX_KC-383A CAUSTIC BLOWER | S | 1 | 1 | 1.00 |
Lead time and procurement
Lead time 20 ± 13 days (PO history, 4 PO lines) · on-time 42%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 28 Jan 2026 | PR06 Regular replenishment | 79 | Rp 219,002 | 04 Feb 2026 | 7 d |
| 16 Sept 2025 | PR06 Regular replenishment | 102 | Rp 231,670 | 27 Sept 2025 | 11 d |
| 24 Aug 2025 | PR06 Regular replenishment | 101 | Rp 230,858 | 11 Sept 2025 | 18 d |
| 01 Jul 2025 | PR03 Regular replenishment | 190 | Rp 215,202 | 05 Aug 2025 | 35 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 30 Oct 2026 | PX_PP-1063 | Lube oil change | 0.72 |
| 01 Mar 2027 | PX_PP-1063 | Lube oil change | 0.72 |
| 01 Jul 2027 | PX_PP-1063 | Lube oil change | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Medium | PX_KC-365C | KC-365C lube oil filter DP high |
| 15 Sept 2026 | Medium | PX_PP-1583A | Replace lamp as per PM finding |
| 03 Sept 2026 | Low | PX_KC-226 | KC-226 bearing temp high |
| 21 Aug 2026 | Low | PX_KC-226 | KC-226 high vibration |
| 03 Aug 2026 | Medium | PX_KC-671D | KC-671D bearing temp high |
| 26 Jul 2026 | Medium | PX_KC-365C | Inspect coupling KC-365C |
| 07 Jun 2026 | High | PX_KC-671D | Install scaffolding at KC-671D |
| 28 Feb 2026 | Medium | PX_KC-137A | Overhaul |
| 16 Jan 2026 | Low | PX_KC-226 | KC-226 bearing temp high |
| 10 Dec 2025 | Medium | PX_KC-752A | Replace lamp as per PM finding |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 09 Aug 2026 | 1 | 201000001982 | Corrective |
| 23 Jul 2026 | 4 | 201000027503 | Corrective |
| 07 Jul 2026 | 1 | 201000003402 | Corrective |
| 24 May 2026 | 20 | 201000004824 | Corrective |
| 21 May 2026 | 20 | 201000007134 | Corrective |
| 21 May 2026 | 200 | 201000013564 | Corrective |
| 18 Jan 2026 | 20 | 201000037028 | Corrective |
| 14 Jan 2026 | 200 | 201000033216 | Corrective |
| 06 Jan 2026 | 4 | 203000006950 | Turnaround |
| 27 Dec 2025 | 5 | 203000001878 | Turnaround |
| 08 Dec 2025 | 4 | 201000007291 | Corrective |
| 05 Dec 2025 | 4 | 203000014228 | Turnaround |
| 10 Nov 2025 | 4 | 201000012771 | Corrective |
| 09 Nov 2025 | 1 | 203000030725 | Turnaround |
| 29 Sept 2025 | 5 | 201000005438 | Corrective |