GASKET,SW,3/4IN,300#,GRAPHITE

Material 4100014256 · GASKET · Plant 1000

ASafety-criticalReorderCriticalStockout
Material
4100014256
Category
GASKET
Base unit
EA
MRP type
Non Stock
Criticality
A (12 of 23 FuncLocs A/B, 2 safety/shutdown valve)
Supplier
RAJAWALI INSTRUMEN INTERNASIONAL PT
Lead time
49 d · P80 73 d
Unit price
Rp 61,819

Recommendation

  • 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 36 EA/year: 36 unplanned (recency-weighted compound poisson (own history)).
  • 3.Lead time ~49 days; expected demand during lead time 4.9.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 20, order up to 57.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 57 now.
  • 6.Installed on 23 FuncLoc(s), 12 of them criticality A/B.
  • 7.ML early warning: 91% probability of demand in the next 90 days.
Proposed purchase requisition
57 EA
Rp 3.5M · order by 01 Oct 2026
Expected arrival ≈ 49 days
Safety-critical (SCE)ML early warningConvert to Stock ItemLast turnaround used 12Single sourceAbnormal consumption
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
20
safety stock 16
Rec. Max
57
order qty 37
Service level
99.9%
stockout risk now 77%
Unit price
Rp 61,819
PO history
ML early warning: 91% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 74 days ago, 53 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (20 units) excluded from the baseline.

Demand pattern Lumpy · 11 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~15 days.

Installed on 23 functional locations

12 with criticality A/B · 26 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-106
CRACKING FURNACE BF-106
A18230.86
PX_BF-103
CRACKING FURNACE BF-103
A13814.58
PX_KC-732D
METHANOL COMPRESSOR
A163.14
PX_KC-222B
LEAN AMINE COMPRESSOR
A151.85
PX_KC-778A
CONDENSATE COMPRESSOR
A131.43
PX_BF-105-PD33
QO TO QUENCH FITTING
A121.30
PX_HE-1173C
RECYCLE ETHANE PREHEATER
A100.22
PX_PRV-495C
SAFETY VALVE CL-883
A100.04
PX_VD-135A
SEAL OIL DRUM
A400.08
PY_HE-1501B
RECYCLE ETHANE TLE
A100.22
PX_FCV-171A
BY PASS LINE
B100.11
PX_HE-1482D
ETHYLENE TLE
B100.22

Lead time and procurement

Lead time 49 ± 22 days (PO history, 7 PO lines) · on-time 39%

PR dateTypeQtyUnit priceDeliveryLead time
18 Jul 2026PR05
Project / turnaround
21Rp 60,02601 Sept 202645 d
09 Jun 2026PR06
Regular replenishment
19Rp 61,81915 Jul 202636 d
28 Jan 2026PR06
Regular replenishment
20Rp 60,99419 Mar 202650 d
21 Jan 2026PR05
Project / turnaround
13Rp 65,14721 Mar 202659 d
08 Nov 2025PR04
Regular (other)
10Rp 62,03314 Feb 202698 d
27 Sept 2025PR10
Other
8Rp 61,85727 Oct 202530 d
19 Sept 2025PR10
Other
15Rp 61,76705 Dec 202577 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026LowPX_BF-103Leak from packing
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
29 Sept 2026MediumPX_BF-106Decoking follow up BF-106
28 Sept 2026LowPX_BF-106Peep door broken BF-106
22 Sept 2026LowPY_HE-1205BLeak from packing
21 Sept 2026MediumPX_BF-110Replace burner tip BF-110
20 Sept 2026MediumPX_BF-103Leak from packing
19 Sept 2026LowPX_BF-103Leak from packing
19 Sept 2026MediumPX_BF-106Cleaning burner BF-106
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair

Recent goods issues

Posting dateQtyOrderOrder type
28 Jul 20266203000004330Turnaround
19 Jul 20262201000001543Corrective
30 Jun 20262209000022177Other maintenance
14 Apr 20261201000013741Corrective
04 Mar 20261201000006597Corrective
10 Feb 20262203000018609Turnaround
21 Dec 202512203000014056Turnaround
30 Nov 20252209000037038Other maintenance
29 Oct 20251201000039948Corrective
12 Oct 20253201000018947Corrective
16 Sept 20259201000003444Corrective
13 Sept 20255201000003651Corrective
04 Aug 20256201000018575Corrective
24 May 20256201000025924Corrective