Sparely
DU

FILTER ELEMENT,SEAL GAS,3MICRON,P/N FE-8

Material 4100086235 · FILTER ELEMENT · Plant 1000

AReorderCriticalStockout
Material
4100086235
Category
FILTER ELEMENT
Base unit
EA
MRP type
Stock Item
Criticality
A (9 of 15 FuncLocs A/B)
Supplier
MITRA SARANA INTERNASIONAL PT
Lead time
67 d · P80 85 d
Unit price
Rp 7.6M

Recommendation

  • 1.Forecast 29 EA/year: 25 unplanned (recency-weighted compound poisson (own history)) + 4.3 from the maintenance plan.
  • 2.Lead time ~67 days; expected demand during lead time 6.0 (incl. 1.4 planned).
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 18, order up to 26.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 26 now.
  • 5.Installed on 15 FuncLoc(s), 9 of them criticality A/B.
  • 6.ML early warning: 99% probability of demand in the next 90 days.
Proposed purchase requisition
26 EA
Rp 196.5M · order by 01 Oct 2026
Expected arrival ≈ 67 days
ML early warningLast turnaround used 1Single sourceAbnormal consumptionPlanned demand in lead time
On hand / on order
0 / 0
no open PO
Today Min / Max
8 / 25
static parameters in BoM
Rec. Min (reorder point)
18
safety stock 12
Rec. Max
26
order qty 8
Service level
99.9%
stockout risk now 95%
Unit price
Rp 7.6M
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 10 days ago, 18 failure notifications on its equipment in 90 days, 3 planned jobs in 90 days, 6 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (4 units) excluded from the baseline.

Demand pattern Lumpy · 24 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 8.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~22 days.

Installed on 15 functional locations

9 with criticality A/B · 15 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-717
FLUSHING OIL COMPRESSOR
A194.00
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KC-226
HYDROGEN AIR COMPRESSOR
A162.28
PX_KC-867D
CONDENSATE FAN
A162.71
PX_KC-316D
METHANOL FAN
A151.43
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KC-279C
C3 RECYCLE COMPRESSOR
A131.43
PX_KC-778A
CONDENSATE COMPRESSOR
A131.43
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_KT-383A
TURBINE FOR KC-383A
S173.67
PX_KC-879A
CONDENSATE FAN
S162.71
PX_KT-264A
TURBINE FOR KC-264A
S142.39

Lead time and procurement

Lead time 67 ± 35 days (PO history, 11 PO lines) · on-time 34%

PR dateTypeQtyUnit priceDeliveryLead time
13 Aug 2026PR03
Regular replenishment
13Rp 7.7M21 Sept 202639 d
18 Jul 2026PR03
Regular replenishment
20Rp 7.6M24 Aug 202637 d
02 Jun 2026PR03
Regular replenishment
14Rp 7.8M25 Jul 202653 d
08 May 2026PR03
Regular replenishment
8Rp 7.6M27 Jun 202650 d
28 Apr 2026PR03
Regular replenishment
5Rp 7.4M18 Sept 2026143 d
15 Apr 2026PR03
Regular replenishment
18Rp 7.2M04 Jul 202680 d
22 Jan 2026PR03
Regular replenishment
8Rp 7.7M17 Apr 202685 d
03 Jan 2026PR03
Regular replenishment
6Rp 7.5M24 Apr 2026111 d
15 Nov 2025PR05
Project / turnaround
13Rp 7.4M01 Feb 202678 d
03 Sept 2025PR03
Regular replenishment
14Rp 7.7M07 Oct 202534 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Oct 2026PX_KC-373BFilter element replacement0.72
01 Nov 2026PX_KC-316DFilter element replacement0.72
26 Dec 2026PX_KT-264ATurbine major overhaul0.72
21 Jan 2027PX_KC-279CFilter element replacement0.72
02 Apr 2027PX_KC-373BFilter element replacement0.72
23 Jul 2027PX_KC-279CFilter element replacement0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Sept 2026LowPX_KC-879AInspect coupling KC-879A
21 Sept 2026LowPX_KC-717Leak from packing
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
17 Sept 2026MediumPX_KC-867DLeak from packing
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
07 Sept 2026MediumPX_KC-879AReplace lamp as per PM finding
05 Sept 2026MediumPX_KC-279COverhaul
03 Sept 2026LowPX_KC-226KC-226 bearing temp high
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A

Recent goods issues

Posting dateQtyOrderOrder type
21 Sept 20261201000037306Corrective
11 Sept 20261203000039516Turnaround
20 Aug 20261201000024327Corrective
02 Aug 20261201000008499Corrective
28 Jul 20261201000000379Corrective
23 Jul 20262201000012032Corrective
13 Jul 20261201000000855Corrective
08 Jul 20265201000003402Corrective
29 Apr 20263201000019885Corrective
28 Jan 20263201000038343Corrective
24 Jan 20261201000025164Corrective
21 Jan 20261203000029956Turnaround
15 Jan 20261201000012328Corrective
14 Jan 20261201000029496Corrective
13 Jan 20261201000005022Corrective