SCREW,TAPPING,M6X16MM,SS304
Material 4100098225 · SCREW · Plant 1000
AReorderCriticalStockout
- Material
- 4100098225
- Category
- SCREW
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (3 of 5 FuncLocs A/B)
- Supplier
- RAJAWALI INSTRUMEN INTERNASIONAL PT
- Lead time
- 20 d · P80 25 d
- Unit price
- Rp 1,780
Recommendation
- 1.Forecast 1,382 EA/year: 1,382 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~20 days; expected demand during lead time 75.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 465, order up to 1,847.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 1,847 now.
- 5.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
- 6.ML early warning: 98% probability of demand in the next 90 days.
Proposed purchase requisition
1,847 EA
Rp 3.3M · order by 01 Oct 2026
Expected arrival ≈ 20 days
ML early warningLast turnaround used 190Single sourceAbnormal consumption
On hand / on order
0 / 0
no open PO
Today Min / Max
265 / 687
static parameters in BoM
Rec. Min (reorder point)
465
safety stock 391
Rec. Max
1,847
order qty 1,382
Service level
100.0%
stockout risk now 55%
Unit price
Rp 1,780
PO history
ML early warning: 98% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 7 issue days in the last 180 days, last issue 66 days ago, 22 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 8 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1,190 units) excluded from the baseline.
Demand pattern Erratic · 24 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~10 days.
Installed on 5 functional locations
3 with criticality A/B · 10,294 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-103 CRACKING FURNACE BF-103 | A | 50 | 38 | 14.58 |
| PX_JBX-1777A JUNCTION BOX | A | 120 | 0 | 0.01 |
| PX_JBX-977B JUNCTION BOX | B | 5,037 | 0 | 0.01 |
| PX_JBX-1817B JUNCTION BOX | C | 5,037 | 2 | 0.44 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 50 | 41 | 14.58 |
Lead time and procurement
Lead time 20 ± 9 days (PO history, 20 PO lines) · on-time 39%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 31 Aug 2026 | PR03 Regular replenishment | 1,297 | Rp 1,723 | 29 Sept 2026 | 29 d |
| 19 Aug 2026 | PR03 Regular replenishment | 821 | Rp 1,738 | 02 Sept 2026 | 14 d |
| 20 Jun 2026 | PR03 Regular replenishment | 2,001 | Rp 1,829 | 27 Jun 2026 | 7 d |
| 06 Jun 2026 | PR03 Regular replenishment | 1,099 | Rp 1,762 | 20 Jun 2026 | 14 d |
| 13 May 2026 | PR06 Regular replenishment | 540 | Rp 1,763 | 07 Jun 2026 | 25 d |
| 05 May 2026 | PR03 Regular replenishment | 656 | Rp 1,784 | 28 May 2026 | 23 d |
| 24 Apr 2026 | PR06 Regular replenishment | 1,520 | Rp 1,785 | 26 May 2026 | 32 d |
| 09 Apr 2026 | PR03 Regular replenishment | 766 | Rp 1,808 | 02 May 2026 | 23 d |
| 17 Mar 2026 | PR03 Regular replenishment | 901 | Rp 1,787 | 30 Mar 2026 | 13 d |
| 23 Feb 2026 | PR06 Regular replenishment | 863 | Rp 1,719 | 06 Mar 2026 | 11 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 21 Sept 2026 | Medium | PX_BF-110 | Replace burner tip BF-110 |
| 20 Sept 2026 | Medium | PX_BF-103 | Leak from packing |
| 19 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 17 Sept 2026 | Medium | PX_BF-110 | Install scaffolding at BF-110 |
| 15 Sept 2026 | Medium | PX_BF-103 | Replace lamp as per PM finding |
| 15 Sept 2026 | Medium | PX_BF-110 | Decoking follow up BF-110 |
| 11 Sept 2026 | Medium | PX_BF-103 | Decoking follow up BF-103 |
| 11 Sept 2026 | Medium | PX_BF-110 | Leak from packing |
| 03 Sept 2026 | Low | PX_BF-110 | Hot spot at convection BF-110 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 27 Jul 2026 | 20 | 201000027402 | Corrective |
| 27 Jul 2026 | 20 | 201000028062 | Corrective |
| 15 Jul 2026 | 100 | 201000016400 | Corrective |
| 12 Jun 2026 | 50 | 201000028320 | Corrective |
| 06 Jun 2026 | 100 | 209000018653 | Other maintenance |
| 18 May 2026 | 50 | 201000039669 | Corrective |
| 28 Apr 2026 | 50 | 201000002499 | Corrective |
| 22 Apr 2026 | 200 | 201000007143 | Corrective |
| 18 Feb 2026 | 100 | 201000026224 | Corrective |
| 12 Feb 2026 | 50 | 201000032040 | Corrective |
| 22 Jan 2026 | 20 | 201000017359 | Corrective |
| 05 Jan 2026 | 50 | 201000011128 | Corrective |
| 03 Jan 2026 | 1,000 | 201000014604 | Corrective |
| 22 Dec 2025 | 200 | 201000022442 | Corrective |
| 17 Dec 2025 | 50 | 203000039452 | Turnaround |