Sparely
DU

FIREBRICK,INSUL,23,65T,114W,230L

Material 4100072283 · FIREBRICK · Plant 1000

AMonitorInsurance gap
Material
4100072283
Category
FIREBRICK
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
76 d · P80 131 d
Unit price
Rp 157,612 (est.)

Recommendation

  • 1.Forecast 617 EA/year: 617 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~76 days; expected demand during lead time 128.
  • 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 791, order up to 1,187.
  • 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
  • 5.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Insurance spare candidatePrice estimatedLead time estimatedSame description as 8 other material numbers
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
791
safety stock 663
Rec. Max
1,187
order qty 396
Service level
99.6%
stockout risk now 28%
Unit price
Rp 157,612
Category + unit estimate
ML early warning: 2% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 22 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~37 days.

Installed on 2 functional locations

1 with criticality A/B · 10,074 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_BF-102
CRACKING FURNACE BF-102
A5,0377128.72
PX_BF-108
CRACKING FURNACE BF-108
S5,037239.44

Lead time and procurement

Lead time 76 ± 47 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
25 Sept 2026MediumPX_BF-108Repair refractory crack BF-108
24 Sept 2026HighPX_BF-108Leak from packing
23 Sept 2026LowPX_BF-102Replace burner tip BF-102
10 Sept 2026MediumPX_BF-108[MSI-B-26-JJB-193] Permanent repair
07 Sept 2026LowPX_BF-102Thermograph wall BF-102
07 Sept 2026MediumPX_BF-108Leak from packing
06 Sept 2026MediumPX_BF-102Decoking follow up BF-102
03 Sept 2026MediumPX_BF-102Replace lamp as per PM finding
30 Aug 2026HighPX_BF-102Painting BF-102
27 Aug 2026MediumPX_BF-102Decoking follow up BF-102

Recent goods issues

Never issued in the 17-month history.