DIAPHRAGM,ACTUATOR,TYPE VP55,CS
Material 4100046840 · DIAPHRAGM · Plant 1000
AReorderCriticalStockout
- Material
- 4100046840
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (17 of 23 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 134 d · P80 191 d
- Unit price
- Rp 4.4M (est.)
Recommendation
- 1.Forecast 1.9 EA/year: 1.9 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~134 days; expected demand during lead time 0.7.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 6 now.
- 5.Installed on 23 FuncLoc(s), 17 of them criticality A/B.
Proposed purchase requisition
6 EA
Rp 26.3M · order by 01 Oct 2026
Expected arrival ≈ 134 days
Last turnaround used 1Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.9%
stockout risk now 50%
Unit price
Rp 4.4M
Category + unit estimate
ML early warning: 16% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 282 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~46 days.
Installed on 23 functional locations
17 with criticality A/B · 27 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-621 PP-902B OUTLET FLOW | A | 1 | 4 | 1.39 |
| PX_FCV-1054 CONTROL VALVE | A | 1 | 2 | 0.54 |
| PX_TCV-584B TEMPERATURE CONTROL VALVE | A | 1 | 2 | 0.55 |
| PX_FCV-485 CONTROL VALVE | A | 1 | 0 | 0.11 |
| PX_PCV-1780C PRESSURE CONTROL VALVE | A | 1 | 0 | 0.08 |
| PY_PCV-437A BY PASS DUCT | A | 1 | 0 | 0.08 |
| PX_LCV-589B PP-389 LEVEL CONTROL | B | 1 | 2 | 0.55 |
| PX_LCV-482 CL-899 LEVEL CONTROL | B | 1 | 1 | 0.12 |
| PX_LCV-809 LEVEL CONTROL VALVE | B | 1 | 1 | 0.12 |
| PX_PCV-1925B BY PASS DUCT | B | 1 | 1 | 0.08 |
| PX_FCV-407B BY PASS LINE | B | 1 | 0 | 0.11 |
| PX_LCV-1053C HE-1091 LEVEL CONTROL | B | 2 | 0 | 0.12 |
Lead time and procurement
Lead time 134 ± 82 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 17 Sept 2026 | Low | PX_FCV-651 | Overhaul FCV-651 |
| 01 Sept 2026 | Medium | PX_TCV-584B | Leak from packing |
| 20 Aug 2026 | Medium | PX_FCV-651 | [MSI-B-26-RWX-113/M] Replace line |
| 28 Jun 2026 | Medium | PX_FCV-621 | Install scaffolding at FCV-621 |
| 30 May 2026 | Low | PX_LCV-589B | LCV-589B stuck |
| 22 Jan 2026 | Medium | PX_FCV-621 | Leak from packing |
| 07 Dec 2025 | Medium | PX_FCV-1054 | [MSI-B-25-YGT-214/M] Replace line |
| 24 Sept 2025 | Low | PX_FCV-621 | Replace lamp as per PM finding |
| 18 Jul 2025 | High | PX_FCV-621 | FCV-621 stuck |
| 30 May 2025 | Medium | PX_LCV-841C | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 23 Dec 2025 | 1 | 201000020470 | Corrective |
| 17 Nov 2025 | 1 | 203000037311 | Turnaround |