Sparely
DU

SEAL,MECHANICAL,TYPE WB489,NBR

Material 4100005164 · SEAL · Plant 1000

AReduceExcess
Material
4100005164
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (18 of 24 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 13 SET/year: 10 unplanned (recency-weighted compound poisson (own history)) + 2.9 from the maintenance plan.
  • 2.Lead time ~150 days; expected demand during lead time 5.7 (incl. 1.4 planned).
  • 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 15, order up to 17.
  • 4.Stock 160 exceeds the level to keep (17) by 143.
  • 5.Installed on 24 FuncLoc(s), 18 of them criticality A/B.
  • 6.ML early warning: 57% probability of demand in the next 90 days.
ML early warningAbnormal consumptionPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
160 / 0
no open PO
Today Min / Max
8 / 16
static parameters in BoM
Rec. Min (reorder point)
15
safety stock 10
Rec. Max
17
order qty 2
Service level
99.8%
stockout risk now 0%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 57% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 35 days ago, 14 failure notifications on its equipment in 90 days, 2 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 8 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 11.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 24 functional locations

18 with criticality A/B · 35 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-506A
COOLING WATER PUMP
A1238.76
PX_PP-251C
RICH AMINE PUMP
A321.05
PX_PP-588
DILUTION STEAM PUMP
A120.19
PX_PP-1178A
PROPYLENE PUMP
A110.19
PX_PP-1967A
WASH WATER PUMP
A110.19
PX_PP-225A
BOTTOM PUMP
A110.62
PX_PP-1013A
SLOP OIL PUMP
A100.19
PX_PP-1363
CAUSTIC PUMP
A100.19
PX_PP-765B
QUENCH OIL PUMP
A100.19
PX_PP-136B
RECYCLE ETHANE PUMP
B182.76
PX_PP-1807C
C3 RECYCLE PUMP
B161.47
PX_PP-1637A
DILUTION STEAM PUMP
B120.62

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Oct 2026PY_PP-1584BPump overhaul0.72
01 Dec 2026PX_PP-1106APump overhaul0.72
02 Apr 2027PX_PP-1178APump overhaul0.72
02 Jun 2027PX_PP-1941APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026MediumPX_PP-136BOil leak at PP-136B bearing housing
24 Sept 2026LowPX_PP-1106AReplace bearing PP-1106A
14 Sept 2026MediumPX_PP-1941AReplace lamp as per PM finding
11 Sept 2026LowPX_PP-506APP-506A high vibration
09 Sept 2026MediumPX_PP-506AReplace lamp as per PM finding
25 Aug 2026MediumPX_PP-1106APP-1106A high vibration
23 Aug 2026MediumPX_PP-136BPP-136B seal leak
23 Aug 2026MediumPX_PP-1891BReplace bearing PP-1891B
12 Aug 2026MediumPX_PP-588Install scaffolding at PP-588
06 Aug 2026MediumPX_PP-1106AOverhaul PP-1106A

Recent goods issues

Posting dateQtyOrderOrder type
27 Aug 20262201000029977Corrective
05 Aug 20261201000006273Corrective
07 Jun 20261201000009207Corrective
06 Jun 20261201000000723Corrective
30 Jan 20261201000033159Corrective
22 Jan 20261201000006322Corrective
17 Sept 20252201000032231Corrective
17 Sept 20254201000032231Corrective
22 Aug 20251201000006098Corrective