Sparely
DU

SEAL,LABYRINTH,SIZE CH566,CS

Material 4100084466 · SEAL · Plant 1000

AReorderNormalTAM reserve
Material
4100084466
Category
SEAL
Base unit
SET
MRP type
Stock Item
Criticality
A (18 of 40 FuncLocs A/B)
Supplier
No PO history
Lead time
150 d · P80 213 d
Unit price
Rp 94.6M (est.)

Recommendation

  • 1.Forecast 4.9 SET/year: 3.5 unplanned (installed-base failure prior (no history)) + 1.4 from the maintenance plan.
  • 2.Lead time ~150 days; expected demand during lead time 2.9 (incl. 1.4 planned).
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 9.
  • 4.On hand 3 + on order 0 is at or below the reorder point: order 6 now.
  • 5.Used only during the last turnaround (1 SET): keep it for the next one instead of treating it as slow-moving.
  • 6.Installed on 40 FuncLoc(s), 18 of them criticality A/B.
Proposed purchase requisition
6 SET
Rp 567.5M · order by 01 Oct 2026
Expected arrival ≈ 150 days
Last turnaround used 1Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 6
Rec. Max
9
order qty 1
Service level
99.9%
stockout risk now 41%
Unit price
Rp 94.6M
Category + unit estimate
ML early warning: 18% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 34 failure notifications on its equipment in 90 days, 2 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 5.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 40 functional locations

18 with criticality A/B · 51 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KC-226
HYDROGEN AIR COMPRESSOR
A262.28
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KC-222B
LEAN AMINE COMPRESSOR
A151.85
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KC-752A
CONDENSATE BLOWER
A141.85
PX_KC-671D
FEED BLOWER
A431.00
PX_KC-778A
CONDENSATE COMPRESSOR
A131.43
PX_KC-235D
DEMIN WATER FAN
A121.00
PX_KC-391D
QUENCH WATER COMPRESSOR
A121.43
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_KT-513
TURBINE FOR KC-513
A321.53

Lead time and procurement

Lead time 150 ± 65 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Nov 2026PX_KC-235DCompressor major overhaul0.72
26 Dec 2026PX_KT-264ATurbine major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-365CKC-365C lube oil filter DP high
26 Sept 2026EmergencyPX_KC-773AInspect coupling KC-773A
24 Sept 2026LowPX_KC-879AInspect coupling KC-879A
23 Sept 2026MediumPX_KC-513KC-513 high vibration
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
16 Sept 2026MediumPX_KC-891AKC-891A high vibration
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
15 Sept 2026LowPX_KC-773AInstall scaffolding at KC-773A
07 Sept 2026MediumPX_KC-513Inspect coupling KC-513

Recent goods issues

Posting dateQtyOrderOrder type
27 Dec 20251203000006078Turnaround
Sparely