Sparely
DU

DIAPHRAGM,ACTUATOR,TYPE QT820,NBR

Material 4100046941 · DIAPHRAGM · Plant 1000

AReorderCriticalStockout
Material
4100046941
Category
DIAPHRAGM
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 9 FuncLocs A/B)
Supplier
No PO history
Lead time
134 d · P80 191 d
Unit price
Rp 4.4M (est.)

Recommendation

  • 1.Forecast 0.0 EA/year: 0.0 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~134 days; expected demand during lead time 0.0.
  • 3.A 98.6% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 1 now.
  • 5.Installed on 9 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
1 EA
Rp 4.4M · order by 01 Oct 2026
Expected arrival ≈ 134 days
Last turnaround used 1Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
98.6%
stockout risk now 1%
Unit price
Rp 4.4M
Category + unit estimate
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 38.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~46 days.

Installed on 9 functional locations

2 with criticality A/B · 15 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TCV-1784
TEMPERATURE CONTROL VALVE
A100.12
PX_LCV-386B
PP-1598B LEVEL CONTROL
B200.12
PX_FCV-338
HE-403A OUTLET FLOW
C100.11
PX_FCV-367
HE-648C OUTLET FLOW
C100.11
PX_PCV-1065
PRESSURE CONTROL VALVE
C400.08
PX_PCV-812C
PP-1934A PRESSURE CONTROL
C100.08
PX_TCV-256
CL-1708 TEMP CONTROL
C300.12
PY_LCV-1843A
HE-1008A LEVEL CONTROL
C100.12
PX_TCV-697A
HE-113B TEMP CONTROL
S110.12

Lead time and procurement

Lead time 134 ± 82 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
02 Aug 2025MediumPX_TCV-697AInstall scaffolding at TCV-697A

Recent goods issues

Posting dateQtyOrderOrder type
14 Nov 20251203000023445Turnaround