CERAMIC FIBER,BLANKET,25T,96KG/M3,1430C
Material 4100075392 · CERAMIC FIBER · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100075392
- Category
- CERAMIC FIBER
- Base unit
- RL
- MRP type
- Non Stock
- Criticality
- A (7 of 10 FuncLocs A/B)
- Supplier
- CAHAYA LOGAM PRATAMA PT
- Lead time
- 67 d · P80 96 d
- Unit price
- Rp 945,243
Recommendation
- 1.Forecast 62 RL/year: 62 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~67 days; expected demand during lead time 11.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 36, order up to 68.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 68 now.
- 5.Long lead time: 80% of deliveries took up to 96 days and the fastest seen in its category 25 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 10 FuncLoc(s), 7 of them criticality A/B.
- 7.ML early warning: 100% probability of demand in the next 90 days.
- 8.Identical part 4100076909 holds spare stock: transfer 10 RL instead of buying, then buy the remaining 58.
Proposed purchase requisition
58 RL
Rp 54.8M · order by 01 Oct 2026
Expected arrival ≈ 67 days
Long-leadML early warningConvert to Stock ItemLast turnaround used 12Single sourceAbnormal consumptionSame description as 2 other material numbers
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
36
safety stock 25
Rec. Max
68
order qty 32
Service level
99.9%
stockout risk now 93%
Unit price
Rp 945,243
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 21 issue days in the last 180 days, last issue 4 days ago, 107 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (18 units) excluded from the baseline.
Demand pattern Smooth · 61 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 24.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~25 days.
Installed on 10 functional locations
7 with criticality A/B · 35 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_BF-105 CRACKING FURNACE BF-105 | A | 5 | 114 | 42.86 |
| PX_BF-106 CRACKING FURNACE BF-106 | A | 1 | 82 | 30.86 |
| PX_BF-102 CRACKING FURNACE BF-102 | A | 5 | 71 | 28.72 |
| PX_BF-103 CRACKING FURNACE BF-103 | A | 3 | 38 | 14.58 |
| PX_BF-109 CRACKING FURNACE BF-109 | A | 3 | 29 | 11.58 |
| PX_BF-104 CRACKING FURNACE BF-104 | A | 1 | 28 | 11.58 |
| PX_BF-111 CRACKING FURNACE BF-111 | A | 5 | 23 | 9.01 |
| PX_BF-110 CRACKING FURNACE BF-110 | S | 2 | 41 | 14.58 |
| PX_BF-108 CRACKING FURNACE BF-108 | S | 5 | 23 | 9.44 |
| PX_BF-101 CRACKING FURNACE BF-101 | S | 5 | 8 | 3.02 |
Lead time and procurement
Lead time 67 ± 38 days (PO history, 23 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 13 Aug 2026 | PR06 Regular replenishment | 21 | Rp 936,897 | 23 Sept 2026 | 41 d |
| 19 Jun 2026 | PR06 Regular replenishment | 38 | Rp 945,243 | 03 Sept 2026 | 76 d |
| 16 May 2026 | PR01 Import / long-lead | 24 | Rp 928,471 | 02 Sept 2026 | 109 d |
| 09 Mar 2026 | PR06 Regular replenishment | 25 | Rp 959,583 | 27 Apr 2026 | 49 d |
| 16 Feb 2026 | PR05 Project / turnaround | 28 | Rp 986,440 | 10 Jul 2026 | 144 d |
| 09 Feb 2026 | PR06 Regular replenishment | 49 | Rp 951,331 | 23 Mar 2026 | 42 d |
| 23 Dec 2025 | PR06 Regular replenishment | 33 | Rp 939,406 | 18 Jan 2026 | 26 d |
| 20 Dec 2025 | PR01 Import / long-lead | 39 | Rp 961,911 | 02 Apr 2026 | 103 d |
| 17 Nov 2025 | PR03 Regular replenishment | 31 | Rp 964,615 | 02 Feb 2026 | 77 d |
| 10 Nov 2025 | PR01 Import / long-lead | 16 | Rp 922,095 | 22 Jan 2026 | 73 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Low | PX_BF-103 | Leak from packing |
| 29 Sept 2026 | High | PX_BF-105 | Repair refractory crack BF-105 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 29 Sept 2026 | Medium | PX_BF-106 | Decoking follow up BF-106 |
| 28 Sept 2026 | Low | PX_BF-106 | Peep door broken BF-106 |
| 25 Sept 2026 | Medium | PX_BF-108 | Repair refractory crack BF-108 |
| 24 Sept 2026 | High | PX_BF-108 | Leak from packing |
| 23 Sept 2026 | Low | PX_BF-102 | Replace burner tip BF-102 |
| 22 Sept 2026 | Medium | PX_BF-111 | Install cover plate BF-111 |
| 21 Sept 2026 | Medium | PX_BF-104 | Cleaning burner BF-104 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 27 Sept 2026 | 2 | 201000031834 | Corrective |
| 25 Sept 2026 | 1 | 209000029477 | Other maintenance |
| 23 Sept 2026 | 1 | 209000029477 | Other maintenance |
| 11 Sept 2026 | 3 | 201000031756 | Corrective |
| 09 Sept 2026 | 1 | 201000016998 | Corrective |
| 01 Sept 2026 | 1 | 204000037316 | Preventive |
| 21 Aug 2026 | 1 | 204000030403 | Preventive |
| 28 Jul 2026 | 1 | 201000004503 | Corrective |
| 10 Jul 2026 | 1 | 201000029268 | Corrective |
| 01 Jul 2026 | 1 | 201000011761 | Corrective |
| 29 Jun 2026 | 1 | 201000006253 | Corrective |
| 27 Jun 2026 | 2 | 201000029042 | Corrective |
| 11 Jun 2026 | 1 | 201000037853 | Corrective |
| 04 Jun 2026 | 2 | 209000018653 | Other maintenance |
| 28 May 2026 | 4 | 201000023249 | Corrective |