TRIM SET,CONTROL VALVE,TYPE FG409,A105
Material 4100043354 · TRIM SET · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100043354
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (9 of 20 FuncLocs A/B)
- Supplier
- SINAR SEJAHTERA LESTARI PT
- Lead time
- 177 d · P80 264 d
- Unit price
- Rp 189.6M
Recommendation
- 1.Forecast 6.0 SET/year: 6.0 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~177 days; expected demand during lead time 2.9.
- 3.A 99.3% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 10.
- 4.On hand 0 + on order 3 is at or below the reorder point: order 7 now.
- 5.Long lead time: 80% of deliveries took up to 264 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 20 FuncLoc(s), 9 of them criticality A/B.
Proposed purchase requisition
7 SET
Rp 1.3B · order by 01 Oct 2026
Expected arrival ≈ 177 days
Needs Management sign-off before it reaches the PR draft
Long-leadConvert to Stock ItemLast turnaround used 1Single sourceOpen PO
On hand / on order
0 / 3
next delivery 08 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 6
Rec. Max
10
order qty 2
Service level
99.3%
stockout risk now 37%
Unit price
Rp 189.6M
PO history
ML early warning: 16% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 6 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (5 units) excluded from the baseline.
Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 7.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.
Installed on 20 functional locations
9 with criticality A/B · 27 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PCV-1887C BY PASS DUCT | A | 1 | 2 | 0.94 |
| PX_TCV-749 PP-136B TEMP CONTROL | A | 2 | 1 | 0.55 |
| PX_FCV-1156C PP-1323A OUTLET FLOW | A | 3 | 0 | 0.11 |
| PX_PCV-262 VD-1729 PRESSURE CONTROL | A | 1 | 0 | 0.08 |
| PX_TCV-546 PP-1168A TEMP CONTROL | A | 1 | 0 | 0.12 |
| PX_FCV-879A CONTROL VALVE | B | 2 | 3 | 1.39 |
| PX_LCV-381 LEVEL CONTROL VALVE | B | 1 | 3 | 0.97 |
| PX_FCV-545 BY PASS LINE | B | 1 | 2 | 0.54 |
| PX_LCV-965 LEVEL CONTROL VALVE | B | 1 | 0 | 0.12 |
| PX_FCV-870 PP-1748 OUTLET FLOW | C | 1 | 2 | 0.54 |
| PX_PCV-1300 BY PASS DUCT | C | 1 | 1 | 0.08 |
| PX_PCV-247 PRESSURE CONTROL VALVE | C | 2 | 1 | 0.08 |
Lead time and procurement
Lead time 177 ± 89 days (PO history, 4 PO lines) · on-time 33%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 28 Jan 2026 | PR06 Regular replenishment | 6 | Rp 192.4M | 31 May 2026 | 123 d |
| 10 Nov 2025 | PR06 Regular replenishment | 3 | Rp 191.5M | 20 Feb 2026 | 102 d |
| 16 Jul 2025 | PR06 Regular replenishment | 3 | Rp 189.6M | 08 Nov 2026 open | 480 d |
| 26 Jun 2025 | PR06 Regular replenishment | 7 | Rp 182.8M | 25 Feb 2026 | 244 d |
| 23 Jun 2025 | PR03 Regular replenishment | 5 | Rp 186.3M | 13 Apr 2026 | 294 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 15 Sept 2026 | Medium | PX_FCV-879A | FCV-879A; valve hunting |
| 18 Aug 2026 | Medium | PX_LCV-381 | LCV-381; valve hunting |
| 11 Aug 2026 | Medium | PX_FCV-870 | [MSI-B-26-FHG-172/M] Replace line |
| 25 Jun 2026 | Medium | PX_PCV-1887C | Install cover plate for MCP cracking |
| 03 Apr 2026 | Low | PX_LCV-381 | Overhaul LCV-381 |
| 04 Nov 2025 | Medium | PX_FCV-545 | Replace lamp as per PM finding |
| 15 Oct 2025 | Medium | PX_FCV-879A | Replace lamp as per PM finding |
| 16 Jul 2025 | Medium | PX_PCV-1887C | PCV-1887C stuck |
| 12 Jun 2025 | Medium | PX_TCV-749 | Install cover plate for MCP cracking |
| 08 Jun 2025 | Low | PX_FCV-879A | FCV-879A passing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 25 Sept 2026 | 1 | 201000034328 | Corrective |
| 10 Sept 2026 | 2 | 201000020197 | Corrective |
| 07 Jan 2026 | 2 | 201000026842 | Corrective |
| 22 Nov 2025 | 1 | 203000020131 | Turnaround |
| 21 Nov 2025 | 1 | 201000024776 | Corrective |
| 20 Nov 2025 | 1 | 201000024776 | Corrective |
| 06 Nov 2025 | 1 | 201000031068 | Corrective |
| 28 Aug 2025 | 2 | 203000006603 | Turnaround |
| 26 Aug 2025 | 2 | 203000006603 | Turnaround |