Sparely
DU

IMPELLER,SIZE FY592,NBR

Material 4100006884 · IMPELLER · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100006884
Category
IMPELLER
Base unit
EA
MRP type
Non Stock
Criticality
A (27 of 35 FuncLocs A/B)
Supplier
EUROSEAL TECHNIK GMBH
Lead time
194 d · P80 247 d
Unit price
Rp 216.6M

Recommendation

  • 1.Forecast 16 EA/year: 10 unplanned (recency-weighted compound poisson (own history)) + 5.7 from the maintenance plan.
  • 2.Lead time ~194 days; expected demand during lead time 9.7 (incl. 4.3 planned).
  • 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 21, order up to 23.
  • 4.On hand 0 + on order 9 is at or below the reorder point: order 14 now.
  • 5.Long lead time: 80% of deliveries took up to 247 days and the fastest seen in its category 105 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 35 FuncLoc(s), 27 of them criticality A/B.
  • 7.ML early warning: 63% probability of demand in the next 90 days.
Proposed purchase requisition
14 EA
Rp 3.0B · order by 01 Oct 2026
Expected arrival ≈ 194 days
Needs Management sign-off before it reaches the PR draft
Long-leadML early warningConvert to Stock ItemLast turnaround used 5Single sourceOpen POPlanned demand in lead time
On hand / on order
0 / 9
next delivery 04 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
21
safety stock 12
Rec. Max
23
order qty 2
Service level
99.7%
stockout risk now 57%
Unit price
Rp 216.6M
PO history
ML early warning: 63% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 178 days ago, 20 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (5 units) excluded from the baseline.

Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 13.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~105 days.

Installed on 35 functional locations

27 with criticality A/B · 45 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-902B
BFW PUMP
A182.33
PX_PP-888A
CONDENSATE PUMP
A161.90
PX_PP-408B
METHANE PUMP
A441.90
PX_PP-1022
QUENCH WATER PUMP
A131.47
PX_PP-1121
DILUTION STEAM PUMP
A320.62
PX_PP-1991A
FEED PUMP
A120.62
PX_PP-807B
INHIBITOR PUMP
A421.05
PX_PP-387
INHIBITOR PUMP
A110.62
PX_PP-592
FLUSHING OIL PUMP
A110.19
PX_PP-1945D
BOTTOM PUMP
A100.19
PX_PP-508D
FEED PUMP
A100.19
PX_PP-604C
BOTTOM PUMP
A100.19

Lead time and procurement

Lead time 194 ± 87 days (PO history, 6 PO lines) · on-time 27%

PR dateTypeQtyUnit priceDeliveryLead time
01 Jun 2026PR05
Project / turnaround
3Rp 217.2M04 Oct 2026
open
125 d
29 Apr 2026PR03
Regular replenishment
3Rp 212.5M31 Aug 2026124 d
26 Feb 2026PR01
Import / long-lead
6Rp 213.7M12 Feb 2027
open
351 d
22 Jan 2026PR10
Other
3Rp 228.3M26 Sept 2026247 d
28 Sept 2025PR06
Regular replenishment
4Rp 230.4M31 Mar 2026184 d
09 Aug 2025PR06
Regular replenishment
5Rp 225.3M19 Jan 2026163 d
20 Jul 2025PR01
Import / long-lead
8Rp 211.5M24 Sept 2026431 d
19 Jun 2025PR01
Import / long-lead
6Rp 216.1M22 Jul 2026398 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Dec 2026PX_PP-1106APump overhaul0.72
01 Jan 2027PX_PP-508DPump overhaul0.72
01 Mar 2027PX_PP-807BPump overhaul2.86
02 Jul 2027PX_PP-1498CPump overhaul1.43

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026MediumPX_PP-136BOil leak at PP-136B bearing housing
27 Sept 2026MediumPX_PP-807BReplace bearing PP-807B
24 Sept 2026LowPX_PP-1106AReplace bearing PP-1106A
24 Sept 2026LowPX_PP-715ALeak from packing
22 Sept 2026MediumPX_PP-888AOil leak at PP-888A bearing housing
05 Sept 2026LowPX_PP-1899Painting PP-1899
30 Aug 2026MediumPX_PP-1399Install scaffolding at PP-1399
26 Aug 2026MediumPX_PP-1121Oil leak at PP-1121 bearing housing
25 Aug 2026MediumPX_PP-1106APP-1106A high vibration
25 Aug 2026LowPX_PP-1498C[MSI-B-26-LAH-309/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
06 Apr 20262201000005444Corrective
08 Jan 20262201000025203Corrective
27 Dec 20252201000022687Corrective
27 Dec 20251201000022687Corrective
19 Dec 20251201000018318Corrective
16 Dec 20251201000026598Corrective
08 Nov 20252203000033996Turnaround
07 Nov 20251203000033996Turnaround
06 Nov 20252203000033996Turnaround
29 Sept 20251201000005438Corrective