DIAPHRAGM,ACTUATOR,MODEL LB982,VITON
Material 4100046807 · DIAPHRAGM · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100046807
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (24 of 49 FuncLocs A/B)
- Supplier
- GUNUNG PERKASA NUSANTARA PT
- Lead time
- 157 d · P80 191 d
- Unit price
- Rp 13.3M
Recommendation
- 1.Forecast 7.6 EA/year: 6.9 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
- 2.Lead time ~157 days; expected demand during lead time 3.7 (incl. 0.7 planned).
- 3.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 13.
- 4.On hand 0 + on order 5 is at or below the reorder point: order 8 now.
- 5.Long lead time: 80% of deliveries took up to 191 days and the fastest seen in its category 46 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 49 FuncLoc(s), 24 of them criticality A/B.
- 7.ML early warning: 87% probability of demand in the next 90 days.
Proposed purchase requisition
8 EA
Rp 106.8M · order by 01 Oct 2026
Expected arrival ≈ 157 days
Long-leadML early warningConvert to Stock ItemLast turnaround used 2Single sourceOpen POPlanned demand in lead time
On hand / on order
0 / 5
next delivery 01 Nov 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 7
Rec. Max
13
order qty 3
Service level
99.7%
stockout risk now 20%
Unit price
Rp 13.3M
PO history
ML early warning: 87% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 52 days ago, 6 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (2 units) excluded from the baseline.
Demand pattern Intermittent · 7 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 5.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~46 days.
Installed on 49 functional locations
24 with criticality A/B · 64 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PY_FCV-894 CONDENSATE FLOW CONTROL | A | 2 | 2 | 0.96 |
| PX_TCV-1203B TEMPERATURE CONTROL VALVE | A | 1 | 1 | 0.55 |
| PX_TCV-1344 TEMPERATURE CONTROL VALVE | A | 1 | 1 | 0.12 |
| PX_LCV-1032 LEVEL CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_LCV-173 LEVEL CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_LCV-909B VD-1420A LEVEL CONTROL | A | 1 | 0 | 0.12 |
| PX_LCV-982 HE-1877D LEVEL CONTROL | A | 2 | 0 | 0.12 |
| PX_PCV-1420C KC-957B PRESSURE CONTROL | A | 1 | 0 | 0.08 |
| PX_PCV-380 HE-1557D PRESSURE CONTROL | A | 3 | 0 | 0.08 |
| PX_PCV-984 KC-984C PRESSURE CONTROL | A | 1 | 0 | 0.08 |
| PX_TCV-680 PP-474A TEMP CONTROL | A | 2 | 0 | 0.12 |
| PY_LCV-209D HE-713D LEVEL CONTROL | A | 1 | 0 | 0.12 |
Lead time and procurement
Lead time 157 ± 82 days (PO history + category, 2 PO lines) · on-time 35%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 28 Apr 2026 | PR03 Regular replenishment | 5 | Rp 12.4M | 01 Nov 2027 open | 552 d |
| 15 Oct 2025 | PR06 Regular replenishment | 2 | Rp 13.6M | 29 May 2026 | 226 d |
| 08 Aug 2025 | PR06 Regular replenishment | 3 | Rp 13.3M | 14 Jan 2026 | 159 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Dec 2026 | PY_FCV-1410B | Final Element Overhaul; Control Valve | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Medium | PX_LCV-326A | Leak from packing |
| 07 Sept 2026 | Medium | PY_FCV-1410B | Replace lamp as per PM finding |
| 24 Aug 2026 | Medium | PX_TCV-998 | TCV-998 passing |
| 05 Aug 2026 | Medium | PX_TCV-998 | Leak from packing |
| 02 Aug 2026 | Medium | PX_TCV-998 | [MSI-B-26-EHU-261] Permanent repair |
| 02 Aug 2026 | Medium | PY_FCV-1410B | FCV-1410B; IA leak from regulator |
| 06 May 2026 | Low | PX_LCV-1909 | LCV-1909; valve hunting |
| 02 Dec 2025 | Medium | PX_PCV-1232B | PCV-1232B; small leak at packing |
| 29 Nov 2025 | Low | PY_FCV-894 | Overhaul FCV-894 |
| 15 Oct 2025 | Medium | PY_FCV-1410B | Overhaul FCV-1410B |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 10 Aug 2026 | 1 | 204000013772 | Preventive |
| 26 Jul 2026 | 1 | 201000003691 | Corrective |
| 25 Jul 2026 | 1 | 201000003691 | Corrective |
| 02 Apr 2026 | 1 | 201000003303 | Corrective |
| 06 Feb 2026 | 1 | 201000039107 | Corrective |
| 16 Jan 2026 | 2 | 201000026554 | Corrective |
| 14 Dec 2025 | 1 | 203000027801 | Turnaround |
| 24 Nov 2025 | 1 | 201000017774 | Corrective |
| 14 Nov 2025 | 1 | 203000023445 | Turnaround |
| 25 Aug 2025 | 2 | 201000012030 | Corrective |