Sparely
DU

FLANGE,SO,3/4IN,300#,SS316,RF

Material 4100032969 · FLANGE · Plant 1000

AReorderCriticalStockout
Material
4100032969
Category
FLANGE
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 4 FuncLocs A/B)
Supplier
SAMUDRA SEJAHTERA INTERNASIONAL PT
Lead time
35 d · P80 41 d
Unit price
Rp 127,676

Recommendation

  • 1.Forecast 53 EA/year: 53 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~35 days; expected demand during lead time 5.0.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 26, order up to 80.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 80 now.
  • 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
  • 6.ML early warning: 92% probability of demand in the next 90 days.
Proposed purchase requisition
80 EA
Rp 10.2M · order by 01 Oct 2026
Expected arrival ≈ 35 days
ML early warningLast turnaround used 14Single sourceAbnormal consumption
On hand / on order
0 / 0
no open PO
Today Min / Max
34 / 99
static parameters in BoM
Rec. Min (reorder point)
26
safety stock 21
Rec. Max
80
order qty 54
Service level
100.0%
stockout risk now 69%
Unit price
Rp 127,676
PO history
ML early warning: 92% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 4 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 4 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (14 units) excluded from the baseline.

Demand pattern Erratic · 22 issue days · 2 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~19 days.

Installed on 4 functional locations

3 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_HE-949A
SEAL OIL PREHEATER
A110.65
PX_HE-1256A
REFLUX PREHEATER
A100.22
PX_HE-726A
SLOP OIL EXCHANGER
A100.22
PX_16-FG-21944-B23A-T
PIPE->16 FROM PP-280A TO PP-448
C100.01

Lead time and procurement

Lead time 35 ± 17 days (PO history, 7 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
03 Sept 2026PR03
Regular replenishment
49Rp 126,54820 Sept 202617 d
20 May 2026PR03
Regular replenishment
65Rp 133,74028 Jun 202639 d
28 Apr 2026PR04
Regular (other)
72Rp 129,69809 Jun 202642 d
16 Apr 2026PR03
Regular replenishment
64Rp 127,67607 Jun 202652 d
11 Dec 2025PR03
Regular replenishment
63Rp 133,76508 Jan 202628 d
02 Sept 2025PR03
Regular replenishment
36Rp 125,13123 Sept 202521 d
26 Aug 2025PR03
Regular replenishment
60Rp 127,65413 Sept 202518 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
23 Jul 2025LowPX_HE-949ALeak from packing

Recent goods issues

Posting dateQtyOrderOrder type
27 Sept 20262201000039607Corrective
04 Aug 20266204000012685Preventive
26 Jul 20265201000027799Corrective
05 May 20263201000028849Corrective
12 Apr 20263201000001667Corrective
05 Mar 20261201000025919Corrective
13 Feb 20262201000023713Corrective
16 Jan 20269201000030989Corrective
13 Jan 20266201000029496Corrective
27 Dec 202514203000033731Turnaround
24 Dec 20254201000037770Corrective
18 Nov 20254201000021350Corrective
13 Nov 20255201000005014Corrective
02 Oct 20253201000007266Corrective
30 Sept 20254201000033223Corrective