SLEEVE,SHAFT,SIZE QH752,A105
Material 4100009153 · SLEEVE · Plant 1000
BReorderCriticalStockout
- Material
- 4100009153
- Category
- SLEEVE
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- B (2 of 4 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 135 d · P80 210 d
- Unit price
- Rp 8.1M (est.)
Recommendation
- 1.Forecast 0.9 EA/year: 0.1 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
- 2.Lead time ~135 days; expected demand during lead time 0.8 (incl. 0.7 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 3 now.
- 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
3 EA
Rp 24.3M · order by 01 Oct 2026
Expected arrival ≈ 135 days
Convert to Stock ItemPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.9%
stockout risk now 100%
Unit price
Rp 8.1M
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 3 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 48.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~67 days.
Installed on 4 functional locations
2 with criticality A/B · 7 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PP-1577D ETHYLENE PUMP | B | 1 | 2 | 1.05 |
| PX_PP-1583A CAUSTIC PUMP | B | 1 | 2 | 0.62 |
| PX_PP-1154B FLUSHING OIL PUMP | C | 4 | 0 | 0.19 |
| PX_PP-298C FLUSHING OIL PUMP | S | 1 | 3 | 1.47 |
Lead time and procurement
Lead time 135 ± 55 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Oct 2026 | PX_PP-1583A | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 15 Sept 2026 | Medium | PX_PP-1583A | Replace lamp as per PM finding |
| 07 Sept 2026 | Medium | PX_PP-1577D | Replace bearing PP-1577D |
| 08 Jul 2026 | Medium | PX_PP-298C | Replace lamp as per PM finding |
| 27 Jun 2026 | Low | PX_PP-298C | Oil leak at PP-298C bearing housing |
| 29 Aug 2025 | Medium | PX_PP-1577D | Replace lamp as per PM finding |
| 31 Jul 2025 | Low | PX_PP-298C | PP-298C abnormal noise |
| 22 May 2025 | Low | PX_PP-1583A | [MSI-B-25-WEW-215] Permanent repair |
Recent goods issues
Never issued in the 17-month history.