SLEEVE,SHAFT,SIZE QH752,A105

Material 4100009153 · SLEEVE · Plant 1000

BReorderCriticalStockout
Material
4100009153
Category
SLEEVE
Base unit
EA
MRP type
Non Stock
Criticality
B (2 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
135 d · P80 210 d
Unit price
Rp 8.1M (est.)

Recommendation

  • 1.Forecast 0.9 EA/year: 0.1 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~135 days; expected demand during lead time 0.8 (incl. 0.7 planned).
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 3 now.
  • 5.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
3 EA
Rp 24.3M · order by 01 Oct 2026
Expected arrival ≈ 135 days
Convert to Stock ItemPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.9%
stockout risk now 100%
Unit price
Rp 8.1M
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 3 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 48.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~67 days.

Installed on 4 functional locations

2 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1577D
ETHYLENE PUMP
B121.05
PX_PP-1583A
CAUSTIC PUMP
B120.62
PX_PP-1154B
FLUSHING OIL PUMP
C400.19
PX_PP-298C
FLUSHING OIL PUMP
S131.47

Lead time and procurement

Lead time 135 ± 55 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Oct 2026PX_PP-1583APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
15 Sept 2026MediumPX_PP-1583AReplace lamp as per PM finding
07 Sept 2026MediumPX_PP-1577DReplace bearing PP-1577D
08 Jul 2026MediumPX_PP-298CReplace lamp as per PM finding
27 Jun 2026LowPX_PP-298COil leak at PP-298C bearing housing
29 Aug 2025MediumPX_PP-1577DReplace lamp as per PM finding
31 Jul 2025LowPX_PP-298CPP-298C abnormal noise
22 May 2025LowPX_PP-1583A[MSI-B-25-WEW-215] Permanent repair

Recent goods issues

Never issued in the 17-month history.