BEARING,JOURNAL,SIZE MG906,GRAPHITE

Material 4100080619 · BEARING · Plant 1000

ALong-leadReorderCriticalSlow-moving
Material
4100080619
Category
BEARING
Base unit
SET
MRP type
Non Stock
Criticality
A (24 of 42 FuncLocs A/B)
Supplier
ATLAS TURBO SERVICES INC
Lead time
140 d · P80 249 d
Unit price
Rp 130.2M

Recommendation

  • 1.Forecast 13 SET/year: 12 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~140 days; expected demand during lead time 5.4 (incl. 0.7 planned).
  • 3.A 98.9% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 14.
  • 4.On hand 2 + on order 6 is at or below the reorder point: order 6 now.
  • 5.Long lead time: 80% of deliveries took up to 249 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 42 FuncLoc(s), 24 of them criticality A/B.
  • 7.ML early warning: 51% probability of demand in the next 90 days.
Proposed purchase requisition
6 SET
Rp 781.4M · order by 01 Oct 2026
Expected arrival ≈ 140 days
Long-leadML early warningConvert to Stock ItemLast turnaround used 2Single sourceOpen POPlanned demand in lead time
On hand / on order
2 / 6
next delivery 24 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 7
Rec. Max
14
order qty 2
Service level
98.9%
stockout risk now 18%
Unit price
Rp 130.2M
PO history
ML early warning: 51% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 198 days ago, 35 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (3 units) excluded from the baseline.

Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 6.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 42 functional locations

24 with criticality A/B · 54 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KC-308B
REFLUX BLOWER
A162.28
PX_KC-713B
SPENT CAUSTIC FAN
A163.14
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KC-316D
METHANOL FAN
A151.43
PX_KC-479C
DILUTION STEAM COMPRESSOR
A152.71
PX_KT-397A
TURBINE FOR KC-397A
A352.81
PX_KC-671D
FEED BLOWER
A131.00
PX_KC-137A
C4 PRODUCT COMPRESSOR
A221.43
PX_KC-391D
QUENCH WATER COMPRESSOR
A121.43
PX_KC-464A
CONDENSATE BLOWER
A121.43
PX_KC-588
CAUSTIC FAN
A321.00

Lead time and procurement

Lead time 140 ± 55 days (PO history, 4 PO lines) · on-time 35%

PR dateTypeQtyUnit priceDeliveryLead time
27 Jul 2026PR06
Regular replenishment
2Rp 131.3M15 Nov 2026
open
111 d
20 Feb 2026PR06
Regular replenishment
1Rp 130.2M24 Oct 2026
open
246 d
05 Feb 2026PR01
Import / long-lead
3Rp 130.5M14 May 2028
open
829 d
18 Dec 2025PR06
Regular replenishment
3Rp 128.4M28 Aug 2026253 d
20 Sept 2025PR06
Regular replenishment
3Rp 127.2M14 Apr 2026206 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Sept 2026MediumPX_KC-575BInstall scaffolding at KC-575B
26 Sept 2026EmergencyPX_KC-773AInspect coupling KC-773A
23 Sept 2026MediumPX_KC-513KC-513 high vibration
21 Sept 2026MediumPX_KC-843Painting KC-843
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
16 Sept 2026LowPX_KC-843Inspect coupling KC-843
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
15 Sept 2026LowPX_KC-773AInstall scaffolding at KC-773A
10 Sept 2026MediumPX_KC-479CKC-479C bearing temp high
07 Sept 2026MediumPX_KC-513Inspect coupling KC-513

Recent goods issues

Posting dateQtyOrderOrder type
17 Mar 20261201000019600Corrective
28 Feb 20261201000027046Corrective
29 Jan 20261201000006492Corrective
16 Dec 20251201000026400Corrective
19 Nov 20251203000006868Turnaround
16 Nov 20251203000006868Turnaround
01 Sept 20251201000037801Corrective
20 Jul 20251203000031669Turnaround