SEAL,LABYRINTH,TYPE KI535,A182F11
Material 4100084762 · SEAL · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100084762
- Category
- SEAL
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (3 of 6 FuncLocs A/B)
- Supplier
- RAJAWALI REFRAKTORI PRATAMA PT
- Lead time
- 183 d · P80 213 d
- Unit price
- Rp 209.3M
Recommendation
- 1.Forecast 8.4 SET/year: 8.4 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~183 days; expected demand during lead time 4.2.
- 3.A 99.4% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 14.
- 4.On hand 0 + on order 2 is at or below the reorder point: order 12 now.
- 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 6 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
12 SET
Rp 2.5B · order by 01 Oct 2026
Expected arrival ≈ 183 days
Needs Management sign-off before it reaches the PR draft
Long-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 30 Mar 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 8
Rec. Max
14
order qty 2
Service level
99.4%
stockout risk now 62%
Unit price
Rp 209.3M
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 422 days ago, 8 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 6.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.
Installed on 6 functional locations
3 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-854C FEED FAN | A | 1 | 7 | 2.28 |
| PX_KC-479C DILUTION STEAM COMPRESSOR | A | 1 | 5 | 2.71 |
| PX_KC-137A C4 PRODUCT COMPRESSOR | A | 1 | 2 | 1.43 |
| PX_KC-582B CAUSTIC BLOWER | S | 1 | 10 | 3.57 |
| PX_KT-383A TURBINE FOR KC-383A | S | 1 | 7 | 3.67 |
| PX_KC-373B CONDENSATE BLOWER | S | 1 | 0 | 0.57 |
Lead time and procurement
Lead time 183 ± 65 days (PO history + category, 1 PO lines) · on-time 37%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 22 Oct 2025 | PR06 Regular replenishment | 2 | Rp 215.3M | 30 Mar 2027 open | 524 d |
| 17 Jun 2025 | PR03 Regular replenishment | 1 | Rp 203.2M | 24 Mar 2026 | 280 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 22 Sept 2026 | Medium | PX_KC-854C | Overhaul |
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 10 Sept 2026 | Medium | PX_KC-479C | KC-479C bearing temp high |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 01 Sept 2026 | High | PX_KC-582B | KC-582B high vibration |
| 26 Aug 2026 | Low | PX_KC-582B | Painting KC-582B |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 18 Aug 2026 | Low | PX_KC-479C | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 05 Aug 2025 | 2 | 201000012320 | Corrective |