SEAL,LABYRINTH,TYPE KI535,A182F11

Material 4100084762 · SEAL · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100084762
Category
SEAL
Base unit
SET
MRP type
Non Stock
Criticality
A (3 of 6 FuncLocs A/B)
Supplier
RAJAWALI REFRAKTORI PRATAMA PT
Lead time
183 d · P80 213 d
Unit price
Rp 209.3M

Recommendation

  • 1.Forecast 8.4 SET/year: 8.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~183 days; expected demand during lead time 4.2.
  • 3.A 99.4% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 14.
  • 4.On hand 0 + on order 2 is at or below the reorder point: order 12 now.
  • 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 6 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
12 SET
Rp 2.5B · order by 01 Oct 2026
Expected arrival ≈ 183 days
Needs Management sign-off before it reaches the PR draft
Long-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 30 Mar 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 8
Rec. Max
14
order qty 2
Service level
99.4%
stockout risk now 62%
Unit price
Rp 209.3M
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 422 days ago, 8 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 6.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 6 functional locations

3 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-854C
FEED FAN
A172.28
PX_KC-479C
DILUTION STEAM COMPRESSOR
A152.71
PX_KC-137A
C4 PRODUCT COMPRESSOR
A121.43
PX_KC-582B
CAUSTIC BLOWER
S1103.57
PX_KT-383A
TURBINE FOR KC-383A
S173.67
PX_KC-373B
CONDENSATE BLOWER
S100.57

Lead time and procurement

Lead time 183 ± 65 days (PO history + category, 1 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
22 Oct 2025PR06
Regular replenishment
2Rp 215.3M30 Mar 2027
open
524 d
17 Jun 2025PR03
Regular replenishment
1Rp 203.2M24 Mar 2026280 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
22 Sept 2026MediumPX_KC-854COverhaul
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
10 Sept 2026MediumPX_KC-479CKC-479C bearing temp high
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
01 Sept 2026HighPX_KC-582BKC-582B high vibration
26 Aug 2026LowPX_KC-582BPainting KC-582B
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
19 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
18 Aug 2026LowPX_KC-479CLeak from packing

Recent goods issues

Posting dateQtyOrderOrder type
05 Aug 20252201000012320Corrective