SEAT RING,VALVE,TYPE LX216,SS304

Material 4100050171 · SEAT RING · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100050171
Category
SEAT RING
Base unit
EA
MRP type
Stock Item
Criticality
A (19 of 41 FuncLocs A/B)
Supplier
BERKAH REFRAKTORI PRATAMA PT
Lead time
133 d · P80 177 d
Unit price
Rp 5.8M

Recommendation

  • 1.Forecast 5.1 EA/year: 5.1 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~133 days; expected demand during lead time 1.8.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 11.
  • 4.On hand 0 + on order 1 is at or below the reorder point: order 10 now.
  • 5.Long lead time: 80% of deliveries took up to 177 days and the fastest seen in its category 65 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 41 FuncLoc(s), 19 of them criticality A/B.
  • 7.ML early warning: 38% probability of demand in the next 90 days.
Proposed purchase requisition
10 EA
Rp 57.6M · order by 01 Oct 2026
Expected arrival ≈ 133 days
Long-leadML early warningSingle sourceOpen PO
On hand / on order
0 / 1
next delivery 08 Oct 2026
Today Min / Max
4 / 10
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
11
order qty 4
Service level
99.9%
stockout risk now 55%
Unit price
Rp 5.8M
PO history
ML early warning: 38% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 5 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (2 units) excluded from the baseline.

Demand pattern Intermittent · 7 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 7.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~65 days.

Installed on 41 functional locations

19 with criticality A/B · 61 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-1466B
BY PASS DUCT
A120.51
PY_FCV-894
CONDENSATE FLOW CONTROL
A120.96
PX_FCV-1909
VD-1070A OUTLET FLOW
A110.54
PX_PCV-1709B
BY PASS DUCT
A110.08
PX_PCV-629
PRESSURE CONTROL VALVE
A110.08
PX_PCV-1049
PRESSURE CONTROL VALVE
A100.08
PX_PCV-820
HE-1547 PRESSURE CONTROL
A100.08
PX_PCV-827
BY PASS DUCT
A100.08
PX_PCV-984
KC-984C PRESSURE CONTROL
A100.08
PY_PCV-437A
BY PASS DUCT
A300.08
PX_FCV-1047
BOTTOM FLOW CONTROL
B130.96
PX_LCV-907
VD-1467 LEVEL CONTROL
B330.97

Lead time and procurement

Lead time 133 ± 52 days (PO history, 5 PO lines) · on-time 43%

PR dateTypeQtyUnit priceDeliveryLead time
20 Apr 2026PR06
Regular replenishment
1Rp 5.7M08 Oct 2026
open
171 d
13 Feb 2026PR03
Regular replenishment
4Rp 5.8M02 Sept 2026201 d
15 Nov 2025PR04
Regular (other)
3Rp 5.8M03 May 2026169 d
09 Jun 2025PR03
Regular replenishment
2Rp 5.7M31 Aug 202583 d
08 Jun 2025PR06
Regular replenishment
2Rp 5.8M26 Sept 2025110 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
04 Sept 2026LowPX_PCV-1466BPCV-1466B; valve hunting
21 Aug 2026MediumPX_FCV-303Leak from packing
07 Jul 2026MediumUT_LCV-710LCV-710; IA leak from regulator
07 Jun 2026LowPX_LCV-907Replace lamp as per PM finding
02 Jun 2026LowPX_TCV-931AInstall cover plate for MCP cracking
29 May 2026LowPX_PCV-372PCV-372 passing
23 May 2026MediumPX_FCV-1047FCV-1047 passing
05 May 2026MediumPX_LCV-907Replace lamp as per PM finding
23 Apr 2026MediumPX_FCV-134FCV-134 passing
08 Apr 2026MediumPX_PCV-1435PCV-1435; small leak at packing

Recent goods issues

Posting dateQtyOrderOrder type
26 Sept 20261201000028026Corrective
05 Aug 20261204000027988Preventive
30 Nov 20251201000025823Corrective
14 Nov 20251201000001164Corrective
03 Oct 20251201000008171Corrective
31 Aug 20251203000006603Turnaround
26 Aug 20251203000006603Turnaround
24 Aug 20251201000014313Corrective
06 Jun 20251201000005139Corrective