TRIM SET,CONTROL VALVE,TYPE TZ314,A105
Material 4100043505 · TRIM SET · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100043505
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (2 of 7 FuncLocs A/B)
- Supplier
- SINAR INSTRUMEN NUSANTARA PT
- Lead time
- 170 d · P80 213 d
- Unit price
- Rp 23.4M
Recommendation
- 1.Forecast 3.1 SET/year: 3.1 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~170 days; expected demand during lead time 1.4.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 9.
- 4.On hand 0 + on order 1 is at or below the reorder point: order 8 now.
- 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 7 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
8 SET
Rp 187.3M · order by 01 Oct 2026
Expected arrival ≈ 170 days
Long-leadConvert to Stock ItemSingle sourceOpen PO
On hand / on order
0 / 1
next delivery 11 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 6
Rec. Max
9
order qty 2
Service level
99.8%
stockout risk now 58%
Unit price
Rp 23.4M
PO history
ML early warning: 17% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 52 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 2.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.
Installed on 7 functional locations
2 with criticality A/B · 7 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PCV-1049 PRESSURE CONTROL VALVE | A | 1 | 0 | 0.08 |
| PX_TCV-233 TEMPERATURE CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_FCV-1668A BY PASS LINE | C | 1 | 0 | 0.11 |
| PX_LCV-787A LEVEL CONTROL VALVE | C | 1 | 0 | 0.12 |
| PX_PCV-185 BY PASS DUCT | C | 1 | 0 | 0.08 |
| PX_PCV-912A PRESSURE CONTROL VALVE | C | 1 | 0 | 0.08 |
| PY_LCV-1843A HE-1008A LEVEL CONTROL | C | 1 | 0 | 0.12 |
Lead time and procurement
Lead time 170 ± 68 days (PO history, 3 PO lines) · on-time 31%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 22 Mar 2026 | PR06 Regular replenishment | 1 | Rp 23.4M | 11 Nov 2026 open | 234 d |
| 05 Feb 2026 | PR05 Project / turnaround | 1 | Rp 22.6M | 05 Aug 2026 | 181 d |
| 15 May 2025 | PR06 Regular replenishment | 2 | Rp 24.0M | 22 Sept 2025 | 130 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 10 Aug 2026 | 2 | 204000007036 | Preventive |
| 08 Jun 2026 | 2 | 201000037598 | Corrective |
| 20 Nov 2025 | 1 | 201000019339 | Corrective |