SEAL,MECHANICAL,SIZE YV554,SS316

Material 4100005377 · SEAL · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100005377
Category
SEAL
Base unit
SET
MRP type
Non Stock
Criticality
A (7 of 8 FuncLocs A/B)
Supplier
SAMUDRA TEKNOLOGI INTERNASIONAL PT
Lead time
149 d · P80 213 d
Unit price
Rp 161.0M

Recommendation

  • 1.Forecast 5.6 SET/year: 4.9 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~149 days; expected demand during lead time 2.0.
  • 3.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 7.
  • 4.On hand 0 + on order 1 is at or below the reorder point: order 6 now.
  • 5.Long lead time: 80% of deliveries took up to 213 days and the fastest seen in its category 71 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 8 FuncLoc(s), 7 of them criticality A/B.
Proposed purchase requisition
6 SET
Rp 966.0M · order by 01 Oct 2026
Expected arrival ≈ 149 days
Long-leadConvert to Stock ItemSingle sourceOpen PO
On hand / on order
0 / 1
next delivery 18 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
7
order qty 1
Service level
99.6%
stockout risk now 59%
Unit price
Rp 161.0M
PO history
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 217 days ago, 8 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 7.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~71 days.

Installed on 8 functional locations

7 with criticality A/B · 8 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-506A
COOLING WATER PUMP
A1238.76
PX_PP-489A
RICH AMINE PUMP
A100.19
PX_PP-390B
SLOP OIL PUMP
B1197.04
PX_PP-339A
METHANE PUMP
B162.33
PX_PP-121B
REFLUX PUMP
B141.05
PX_PP-123
LEAN AMINE PUMP
B100.19
PX_PP-1370C
FUEL OIL PUMP
B100.19
PX_PP-591A
INHIBITOR PUMP
S100.19

Lead time and procurement

Lead time 149 ± 65 days (PO history + category, 2 PO lines) · on-time 25%

PR dateTypeQtyUnit priceDeliveryLead time
25 Mar 2026PR06
Regular replenishment
1Rp 161.7M23 Sept 2026182 d
08 Dec 2025PR05
Project / turnaround
1Rp 161.0M18 Dec 2026
open
375 d
29 May 2025PR06
Regular replenishment
1Rp 155.4M21 Sept 2025115 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Mar 2027PX_PP-339APump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
11 Sept 2026LowPX_PP-506APP-506A high vibration
09 Sept 2026MediumPX_PP-506AReplace lamp as per PM finding
05 Sept 2026MediumPX_PP-121BPP-121B discharge pressure low
02 Sept 2026LowPX_PP-390BPP-390B high vibration
25 Aug 2026MediumPX_PP-390BPP-390B seal leak
24 Aug 2026MediumPX_PP-121BInstall scaffolding at PP-121B
21 Aug 2026MediumPX_PP-390BInstall scaffolding at PP-390B
13 Aug 2026MediumPX_PP-390BOil leak at PP-390B bearing housing
01 Aug 2026MediumPX_PP-506AOil leak at PP-506A bearing housing
19 Jul 2026LowPX_PP-339APP-339A seal leak

Recent goods issues

Posting dateQtyOrderOrder type
26 Feb 20261201000019616Corrective
06 Nov 20251201000001956Corrective