BEARING,JOURNAL,TYPE PE318,MONEL

Material 4100080790 · BEARING · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100080790
Category
BEARING
Base unit
SET
MRP type
Non Stock
Criticality
A (4 of 8 FuncLocs A/B)
Supplier
RAJAWALI REFRAKTORI PRATAMA PT
Lead time
139 d · P80 268 d
Unit price
Rp 361.7M

Recommendation

  • 1.Forecast 5.3 SET/year: 4.6 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~139 days; expected demand during lead time 1.7.
  • 3.A 96.8% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 5.
  • 4.On hand 0 + on order 1 is at or below the reorder point: order 4 now.
  • 5.Long lead time: 80% of deliveries took up to 268 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 8 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
4 SET
Rp 1.4B · order by 01 Oct 2026
Expected arrival ≈ 139 days
Needs Management sign-off before it reaches the PR draft
Long-leadConvert to Stock ItemSingle sourceOpen PO
On hand / on order
0 / 1
next delivery 26 Mar 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 3
Rec. Max
5
order qty 1
Service level
96.8%
stockout risk now 52%
Unit price
Rp 361.7M
PO history
ML early warning: 15% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 260 days ago, 8 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 8 functional locations

4 with criticality A/B · 12 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_KC-930C
SLOP OIL FAN
A100.57
PX_KT-308B
TURBINE FOR KC-308B
A101.10
PX_KC-620A
DEMIN WATER AIR COMPRESSOR
B121.00
PX_KC-365C
INHIBITOR BLOWER
S473.14
PX_KT-383A
TURBINE FOR KC-383A
S273.67
PX_KT-624A
TURBINE FOR KC-624A
S132.39
PX_KC-373B
CONDENSATE BLOWER
S100.57

Lead time and procurement

Lead time 139 ± 59 days (PO history, 3 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
25 May 2026PR06
Regular replenishment
1Rp 368.3M26 Mar 2027
open
305 d
28 Sept 2025PR03
Regular replenishment
2Rp 344.8M26 Feb 2026151 d
19 May 2025PR06
Regular replenishment
2Rp 361.7M17 Dec 2025212 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Aug 2027PX_KC-620ACompressor major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-365CKC-365C lube oil filter DP high
19 Sept 2026HighPX_KT-383A[MSI-B-26-CWK-358] Permanent repair
16 Sept 2026MediumPX_KT-383AInstall scaffolding at KT-383A
02 Sept 2026LowPX_KT-383AReplace lamp as per PM finding
23 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
19 Aug 2026MediumPX_KT-383AFollow up after steam upset KT-383A
26 Jul 2026MediumPX_KC-365CInspect coupling KC-365C
20 Jul 2026LowPX_KT-856AFollow up after steam upset KT-856A
15 Jul 2026MediumPX_KT-624A[MSI-B-26-RXR-331/M] Replace line
24 May 2026HighPX_KT-383AKT-383A steam leak at gland

Recent goods issues

Posting dateQtyOrderOrder type
14 Jan 20261201000036735Corrective