BEARING,BALL,ANGULAR,NU306-2Z
Material 4100000155 · BEARING · Plant 1000
ALong-leadReduceExcess
- Material
- 4100000155
- Category
- BEARING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (54 of 69 FuncLocs A/B)
- Supplier
- CAHAYA TEKNIK PERSADA PT
- Lead time
- 89 d · P80 103 d
- Unit price
- Rp 1.4M
Recommendation
- 1.Forecast 58 EA/year: 56 unplanned (recency-weighted compound poisson (own history)) + 2.1 from the maintenance plan.
- 2.Lead time ~89 days; expected demand during lead time 14 (incl. 0.7 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 40, order up to 65.
- 4.Stock 70 exceeds the level to keep (65) by 5.
- 5.Long lead time: 80% of deliveries took up to 103 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 69 FuncLoc(s), 54 of them criticality A/B.
- 7.ML early warning: 100% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 6Single sourceAbnormal consumptionOpen POPlanned demand in lead time
On hand / on order
70 / 67
next delivery 01 Oct 2026
Today Min / Max
45 / 87
static parameters in BoM
Rec. Min (reorder point)
40
safety stock 26
Rec. Max
65
order qty 25
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.4M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 17 issue days in the last 180 days, last issue 15 days ago, 51 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 6 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (8 units) excluded from the baseline.
Demand pattern Erratic · 60 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 19.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.
Installed on 69 functional locations
54 with criticality A/B · 73 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-717 FLUSHING OIL COMPRESSOR | A | 1 | 9 | 4.00 |
| PX_KC-854C FEED FAN | A | 1 | 7 | 2.28 |
| PX_KC-226 HYDROGEN AIR COMPRESSOR | A | 1 | 6 | 2.28 |
| PX_KC-867D CONDENSATE FAN | A | 1 | 6 | 2.71 |
| PX_PP-888A CONDENSATE PUMP | A | 1 | 6 | 1.90 |
| PX_KC-222B LEAN AMINE COMPRESSOR | A | 1 | 5 | 1.85 |
| PX_KC-316D METHANOL FAN | A | 1 | 5 | 1.43 |
| PX_KC-479C DILUTION STEAM COMPRESSOR | A | 1 | 5 | 2.71 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KC-279C C3 RECYCLE COMPRESSOR | A | 1 | 3 | 1.43 |
| PX_KC-396 WASH WATER BLOWER | A | 1 | 3 | 1.43 |
| PX_KC-671D FEED BLOWER | A | 1 | 3 | 1.00 |
Lead time and procurement
Lead time 89 ± 43 days (PO history, 26 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 23 Jul 2026 | PR03 Regular replenishment | 14 | Rp 1.4M | 20 Sept 2026 | 59 d |
| 20 Jul 2026 | PR03 Regular replenishment | 31 | Rp 1.4M | 01 Oct 2026 open | 73 d |
| 20 Jul 2026 | PR03 Regular replenishment | 47 | Rp 1.4M | 13 Sept 2026 | 55 d |
| 12 Jun 2026 | PR06 Regular replenishment | 36 | Rp 1.4M | 03 Sept 2026 | 83 d |
| 02 Jun 2026 | PR03 Regular replenishment | 36 | Rp 1.5M | 14 Dec 2026 open | 195 d |
| 28 Apr 2026 | PR06 Regular replenishment | 49 | Rp 1.5M | 25 Jun 2026 | 58 d |
| 18 Mar 2026 | PR06 Regular replenishment | 41 | Rp 1.4M | 02 Jun 2026 | 76 d |
| 19 Feb 2026 | PR03 Regular replenishment | 32 | Rp 1.4M | 24 Apr 2026 | 64 d |
| 12 Feb 2026 | PR06 Regular replenishment | 27 | Rp 1.5M | 15 May 2026 | 92 d |
| 22 Jan 2026 | PR05 Project / turnaround | 22 | Rp 1.5M | 29 Jul 2026 | 188 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 26 Dec 2026 | PX_KT-264A | Turbine major overhaul | 0.72 |
| 09 Jan 2027 | PX_PP-957A | Pump overhaul | 0.72 |
| 02 Jul 2027 | PX_PP-200A | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Medium | PX_KC-396 | Replace lamp as per PM finding |
| 26 Sept 2026 | Emergency | PX_KC-773A | Inspect coupling KC-773A |
| 22 Sept 2026 | Medium | PX_KC-854C | Overhaul |
| 22 Sept 2026 | Medium | PX_PP-888A | Oil leak at PP-888A bearing housing |
| 21 Sept 2026 | Low | PX_KC-717 | Leak from packing |
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 18 Sept 2026 | Medium | PX_PP-412 | Oil leak at PP-412 bearing housing |
| 17 Sept 2026 | Medium | PX_KC-867D | Leak from packing |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 16 Sept 2026 | 1 | 209000036917 | Other maintenance |
| 09 Aug 2026 | 1 | 201000001248 | Corrective |
| 26 Jul 2026 | 1 | 201000035229 | Corrective |
| 13 Jul 2026 | 2 | 201000028281 | Corrective |
| 12 Jul 2026 | 1 | 201000000855 | Corrective |
| 12 Jul 2026 | 1 | 201000006682 | Corrective |
| 09 Jul 2026 | 1 | 209000016630 | Other maintenance |
| 07 Jul 2026 | 1 | 201000037176 | Corrective |
| 04 Jul 2026 | 2 | 201000014535 | Corrective |
| 03 Jul 2026 | 3 | 201000023944 | Corrective |
| 13 Jun 2026 | 1 | 209000014321 | Other maintenance |
| 11 Jun 2026 | 1 | 201000000811 | Corrective |
| 31 May 2026 | 2 | 204000015505 | Preventive |
| 29 May 2026 | 1 | 201000027832 | Corrective |
| 19 May 2026 | 2 | 201000006651 | Corrective |