BEARING,ROLLER,CYL,1ROW,6313 C3

Material 4100000182 · BEARING · Plant 1000

AReduceExcess
Material
4100000182
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (37 of 51 FuncLocs A/B)
Supplier
DUTA ENERGI ABADI PT
Lead time
46 d · P80 42 d
Unit price
Rp 4.3M

Recommendation

  • 1.Forecast 39 EA/year: 35 unplanned (recency-weighted compound poisson (own history)) + 3.6 from the maintenance plan.
  • 2.Lead time ~46 days; expected demand during lead time 4.4.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 21, order up to 33.
  • 4.Stock 4,534 exceeds the level to keep (33) by 4,501.
  • 5.Installed on 51 FuncLoc(s), 37 of them criticality A/B.
  • 6.ML early warning: 99% probability of demand in the next 90 days.
ML early warningLast turnaround used 4Single sourceAbnormal consumptionOpen PO
On hand / on order
4,534 / 71
next delivery 07 Oct 2026
Today Min / Max
87 / 212
static parameters in BoM
Rec. Min (reorder point)
21
safety stock 17
Rec. Max
33
order qty 12
Service level
99.9%
stockout risk now 0%
Unit price
Rp 4.3M
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 10 issue days in the last 180 days, last issue 7 days ago, 23 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 5 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (5 units) excluded from the baseline.

Demand pattern Smooth · 40 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 13.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 51 functional locations

37 with criticality A/B · 73 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-536A
LUBE OIL BLOWER
A1114.42
PX_KT-856A
TURBINE FOR KC-856A
A172.81
PX_PP-1506
FEED PUMP
A172.76
PX_KC-479C
DILUTION STEAM COMPRESSOR
A152.71
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_PP-1192
FEED PUMP
A251.47
PX_KC-317B
RICH AMINE FAN
A141.85
PX_KC-447
LUBE OIL COMPRESSOR
A141.85
PX_PP-1671-M
MOTOR FOR PP-1671
A140.62
PX_KC-279C
C3 RECYCLE COMPRESSOR
A131.43
PX_PP-207
INHIBITOR PUMP
A331.47
PX_KC-391D
QUENCH WATER COMPRESSOR
A121.43

Lead time and procurement

Lead time 46 ± 46 days (PO history, 13 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
15 Sept 2026PR03
Regular replenishment
27Rp 4.3M31 Oct 2026
open
46 d
06 Sept 2026PR06
Regular replenishment
16Rp 4.3M07 Oct 2026
open
31 d
05 Aug 2026PR03
Regular replenishment
27Rp 4.3M28 Aug 202623 d
19 Jul 2026PR01
Import / long-lead
28Rp 4.3M20 Jan 2027
open
185 d
06 May 2026PR03
Regular replenishment
20Rp 4.4M29 May 202623 d
25 Mar 2026PR06
Regular replenishment
18Rp 4.4M29 Apr 202635 d
13 Jan 2026PR06
Regular replenishment
7Rp 4.1M04 Feb 202622 d
16 Nov 2025PR03
Regular replenishment
24Rp 4.2M27 Nov 202511 d
20 Sept 2025PR03
Regular replenishment
28Rp 4.2M16 Oct 202526 d
20 Aug 2025PR06
Regular replenishment
9Rp 4.2M14 Sept 202525 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72
01 Jan 2027PX_PP-1323Pump overhaul2.15
02 Jul 2027PX_PP-821Pump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Sept 2026MediumPX_PP-1506Replace bearing PP-1506
28 Sept 2026LowPX_KC-886DKC-886D high vibration
24 Sept 2026LowPX_KC-879AInspect coupling KC-879A
22 Sept 2026HighPX_KC-536AOverhaul
10 Sept 2026MediumPX_KC-479CKC-479C bearing temp high
07 Sept 2026MediumPX_KC-879AReplace lamp as per PM finding
05 Sept 2026MediumPX_KC-279COverhaul
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
18 Aug 2026LowPX_KC-479CLeak from packing
17 Aug 2026MediumPX_KC-447Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
24 Sept 20261201000003956Corrective
17 Sept 20261201000017824Corrective
09 Sept 20261201000030502Corrective
18 Aug 20261201000006432Corrective
04 Aug 20261204000012685Preventive
14 Jul 20261201000028281Corrective
12 Jun 20261201000016926Corrective
11 Jun 20263201000031705Corrective
10 Jun 20261201000031705Corrective
07 May 20261201000011178Corrective
28 Feb 20261201000021513Corrective
27 Feb 20261201000001179Corrective
23 Feb 20261201000029300Corrective
17 Feb 20261201000002211Corrective
13 Feb 20261201000033319Corrective