BEARING,BALL,ANGULAR,NU319BDB

Material 4100000238 · BEARING · Plant 1000

AReduceExcess
Material
4100000238
Category
BEARING
Base unit
EA
MRP type
Non Stock
Criticality
A (31 of 40 FuncLocs A/B)
Supplier
DUTA ENERGI ABADI PT
Lead time
39 d · P80 43 d
Unit price
Rp 2.7M

Recommendation

  • 1.Forecast 24 EA/year: 24 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~39 days; expected demand during lead time 2.5.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 11, order up to 23.
  • 4.Stock 68 exceeds the level to keep (23) by 45.
  • 5.Installed on 40 FuncLoc(s), 31 of them criticality A/B.
  • 6.ML early warning: 99% probability of demand in the next 90 days.
ML early warningConvert to Stock ItemLast turnaround used 10Single sourceOpen PO
On hand / on order
68 / 8
next delivery 07 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
11
safety stock 9
Rec. Max
23
order qty 12
Service level
100.0%
stockout risk now 0%
Unit price
Rp 2.7M
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 7 issue days in the last 180 days, last issue 24 days ago, 17 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 6 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (14 units) excluded from the baseline.

Demand pattern Erratic · 31 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 9.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 40 functional locations

31 with criticality A/B · 51 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-902B
BFW PUMP
A182.33
PX_KC-854C
FEED FAN
A172.28
PX_KC-226
HYDROGEN AIR COMPRESSOR
A162.28
PX_KC-316D
METHANOL FAN
A151.43
PX_PP-139
CAUSTIC PUMP
A141.90
PX_KC-671D
FEED BLOWER
A131.00
PX_PP-392A-M
MOTOR FOR PP-392A
A131.05
PX_KC-106B
GASOLINE BLOWER
A121.00
PX_KC-137A
C4 PRODUCT COMPRESSOR
A121.43
PX_KC-435A
FUEL OIL AIR COMPRESSOR
A121.00
PX_KT-513
TURBINE FOR KC-513
A121.53
PX_PP-1157-M
MOTOR FOR PP-1157
A120.19

Lead time and procurement

Lead time 39 ± 19 days (PO history, 18 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
24 Aug 2026PR06
Regular replenishment
11Rp 2.8M24 Sept 202631 d
20 Aug 2026PR06
Regular replenishment
8Rp 2.6M07 Nov 2026
open
79 d
17 Aug 2026PR06
Regular replenishment
18Rp 2.8M27 Sept 202641 d
25 Jun 2026PR06
Regular replenishment
23Rp 2.7M10 Jul 202615 d
10 Jun 2026PR06
Regular replenishment
14Rp 2.8M05 Jul 202625 d
18 Apr 2026PR10
Other
7Rp 2.7M31 May 202643 d
18 Jan 2026PR10
Other
12Rp 2.8M11 Feb 202624 d
10 Jan 2026PR03
Regular replenishment
21Rp 2.7M25 Jan 202615 d
30 Dec 2025PR06
Regular replenishment
22Rp 2.8M04 Feb 202636 d
20 Dec 2025PR06
Regular replenishment
22Rp 2.8M20 Feb 202662 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Aug 2027PX_KC-620ACompressor major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
22 Sept 2026MediumPX_KC-854COverhaul
03 Sept 2026LowPX_KC-226KC-226 bearing temp high
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
23 Aug 2026EmergencyPX_PP-392A-MPP-392A-M high temp
21 Aug 2026LowPX_KC-226KC-226 high vibration
21 Aug 2026MediumPX_KC-624AKC-624A high vibration
11 Aug 2026MediumPX_PP-139Oil leak at PP-139 bearing housing
10 Aug 2026MediumPX_KC-316DOverhaul
10 Aug 2026MediumPX_KC-624ALeak from packing
09 Aug 2026MediumPX_PP-139Install cover plate for MCP cracking

Recent goods issues

Posting dateQtyOrderOrder type
07 Sept 20261201000030378Corrective
26 Aug 20261201000039395Corrective
10 Jul 20261201000026179Corrective
10 Jul 20261204000007631Preventive
16 Jun 20261201000018563Corrective
11 Jun 20261201000019595Corrective
02 Jun 20261201000022564Corrective
22 Apr 20261201000020310Corrective
09 Mar 20262201000034082Corrective
06 Feb 20261203000032991Turnaround
24 Jan 20261201000031722Corrective
16 Jan 20261203000029956Turnaround
09 Jan 20261203000006950Turnaround
08 Jan 20261206000027736Other maintenance
31 Dec 20251201000034801Corrective