BEARING,BALL,1ROW,DEEP GROOVE,6311

Material 4100000256 · BEARING · Plant 1000

AReduceExcess
Material
4100000256
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (16 of 26 FuncLocs A/B)
Supplier
GEMILANG MANDIRI JAYA PT
Lead time
45 d · P80 54 d
Unit price
Rp 540,703

Recommendation

  • 1.Forecast 24 EA/year: 22 unplanned (recency-weighted compound poisson (own history)) + 1.4 from the maintenance plan.
  • 2.Lead time ~45 days; expected demand during lead time 3.5 (incl. 0.7 planned).
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 13, order up to 37.
  • 4.Stock 437 exceeds the level to keep (37) by 400.
  • 5.Installed on 26 FuncLoc(s), 16 of them criticality A/B.
  • 6.ML early warning: 93% probability of demand in the next 90 days.
ML early warningLast turnaround used 12Single sourceAbnormal consumptionOpen POPlanned demand in lead time
On hand / on order
437 / 17
next delivery 29 Oct 2026
Today Min / Max
6 / 15
static parameters in BoM
Rec. Min (reorder point)
13
safety stock 10
Rec. Max
37
order qty 24
Service level
100.0%
stockout risk now 0%
Unit price
Rp 540,703
PO history
ML early warning: 93% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 6 issue days in the last 180 days, last issue 9 days ago, 7 failure notifications on its equipment in 90 days, 2 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (14 units) excluded from the baseline.

Demand pattern Intermittent · 19 issue days · 1 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 6.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 26 functional locations

16 with criticality A/B · 29 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PX_KC-479C
DILUTION STEAM COMPRESSOR
A152.71
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KC-447
LUBE OIL COMPRESSOR
A141.85
PX_KC-396
WASH WATER BLOWER
A131.43
PX_KC-235D
DEMIN WATER FAN
A121.00
PX_PP-1882C
RECYCLE ETHANE PUMP
A120.62
PX_PP-1194B
RICH AMINE PUMP
A100.19
PX_PP-508D-M
MOTOR FOR PP-508D
A100.19
PX_PP-598B-M
MOTOR FOR PP-598B
A100.19
PX_PP-121B
REFLUX PUMP
B141.05
PX_PP-367C
METHANE PUMP
B141.90

Lead time and procurement

Lead time 45 ± 26 days (PO history, 12 PO lines) · on-time 41%

PR dateTypeQtyUnit priceDeliveryLead time
27 Aug 2026PR06
Regular replenishment
17Rp 513,72329 Oct 2026
open
63 d
24 Jul 2026PR03
Regular replenishment
15Rp 514,52217 Sept 202655 d
09 Jul 2026PR03
Regular replenishment
22Rp 541,95422 Jul 202613 d
17 Feb 2026PR06
Regular replenishment
12Rp 526,23219 Mar 202630 d
13 Dec 2025PR03
Regular replenishment
9Rp 547,69229 Jan 202647 d
26 Sept 2025PR06
Regular replenishment
18Rp 542,97206 Nov 202541 d
11 Sept 2025PR03
Regular replenishment
16Rp 529,36329 Oct 202548 d
29 Jul 2025PR03
Regular replenishment
19Rp 539,45101 Sept 202534 d
04 Jun 2025PR05
Project / turnaround
18Rp 556,79410 Sept 202598 d
03 Jun 2025PR03
Regular replenishment
11Rp 558,98002 Jul 202529 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Nov 2026PX_KC-235DCompressor major overhaul0.72
26 Dec 2026PX_KT-264ATurbine major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Sept 2026MediumPX_KC-396Replace lamp as per PM finding
10 Sept 2026MediumPX_KC-479CKC-479C bearing temp high
05 Sept 2026MediumPX_PP-121BPP-121B discharge pressure low
24 Aug 2026MediumPX_PP-121BInstall scaffolding at PP-121B
18 Aug 2026LowPX_KC-479CLeak from packing
17 Aug 2026MediumPX_KC-447Leak from packing
08 Jul 2026MediumPX_KC-422AKC-422A high vibration
07 Jul 2026MediumPX_KC-447Replace lamp as per PM finding
11 Jun 2026LowPX_KT-264ALeak from packing
31 May 2026MediumPX_KC-479C[MSI-B-26-KNK-222/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
22 Sept 20261201000037585Corrective
11 Sept 20261201000028460Corrective
11 Sept 20261201000035065Corrective
22 Aug 20263201000025413Corrective
04 Aug 20261201000010583Corrective
03 Jul 20262201000014145Corrective
08 Jun 20262203000002440Turnaround
15 Apr 20261201000009704Corrective
15 Apr 20264201000012829Corrective
27 Mar 20261204000036669Preventive
31 Jan 20263201000012261Corrective
29 Jan 20262201000036610Corrective
22 Jan 20261201000008172Corrective
09 Jan 20263203000006950Turnaround
09 Jan 20261203000006950Turnaround