BEARING,BALL,1ROW,DEEP GROOVE,7211
Material 4100000320 · BEARING · Plant 1000
AMonitorHealthy
- Material
- 4100000320
- Category
- BEARING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (11 of 19 FuncLocs A/B)
- Supplier
- LANGIT INDUSTRI PRATAMA PT
- Lead time
- 46 d · P80 55 d
- Unit price
- Rp 585,126
Recommendation
- 1.Forecast 13 EA/year: 13 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
- 2.Lead time ~46 days; expected demand during lead time 1.6.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 22.
- 4.Installed on 19 FuncLoc(s), 11 of them criticality A/B.
- 5.ML early warning: 89% probability of demand in the next 90 days.
ML early warningLast turnaround used 2Single sourceOpen PO
On hand / on order
7 / 4
next delivery 03 Nov 2026
Today Min / Max
3 / 9
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 7
Rec. Max
22
order qty 14
Service level
100.0%
stockout risk now 0%
Unit price
Rp 585,126
PO history
ML early warning: 89% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 28 days ago, 7 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (2 units) excluded from the baseline.
Demand pattern Intermittent · 16 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 5.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.
Installed on 19 functional locations
11 with criticality A/B · 23 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 1 | 7 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 2 | 5 | 2.81 |
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_PP-1121 DILUTION STEAM PUMP | A | 1 | 2 | 0.62 |
| PX_PP-1384B COOLING WATER PUMP | A | 1 | 0 | 0.19 |
| PX_PP-1541 DEMIN WATER PUMP | A | 1 | 0 | 0.19 |
| PX_PP-200A-M MOTOR FOR PP-200A | A | 1 | 0 | 0.19 |
| PX_PP-479 SEAL OIL PUMP | B | 1 | 10 | 2.76 |
| PX_PP-1205A DEMIN WATER PUMP | B | 1 | 0 | 0.19 |
| PX_PP-1886B-M MOTOR FOR PP-1886B | B | 1 | 0 | 0.19 |
| PX_PP-291D RECYCLE ETHANE PUMP | B | 4 | 0 | 0.19 |
| PX_PP-1898A INHIBITOR PUMP | C | 1 | 2 | 0.62 |
Lead time and procurement
Lead time 46 ± 21 days (PO history, 6 PO lines) · on-time 53%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 09 Sept 2026 | PR04 Regular (other) | 4 | Rp 606,417 | 03 Nov 2026 open | 55 d |
| 19 Jul 2026 | PR03 Regular replenishment | 6 | Rp 589,657 | 15 Aug 2026 | 27 d |
| 16 Jan 2026 | PR03 Regular replenishment | 9 | Rp 580,595 | 16 Feb 2026 | 31 d |
| 21 Dec 2025 | PR03 Regular replenishment | 10 | Rp 608,828 | 14 Feb 2026 | 55 d |
| 15 Dec 2025 | PR03 Regular replenishment | 7 | Rp 574,853 | 27 Jan 2026 | 43 d |
| 26 Sept 2025 | PR06 Regular replenishment | 5 | Rp 565,268 | 31 Oct 2025 | 35 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Jun 2027 | PX_PP-1541 | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 12 Sept 2026 | Medium | PX_PP-479 | Install scaffolding at PP-479 |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 26 Aug 2026 | Medium | PX_PP-1121 | Oil leak at PP-1121 bearing housing |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 18 Aug 2026 | Medium | PX_PP-479 | Oil leak at PP-479 bearing housing |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 14 Jul 2026 | Low | PX_KC-856A | Install scaffolding at KC-856A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 03 Sept 2026 | 1 | 204000004134 | Preventive |
| 28 Aug 2026 | 1 | 201000023904 | Corrective |
| 09 Jul 2026 | 1 | 201000018688 | Corrective |
| 07 Jun 2026 | 1 | 201000011195 | Corrective |
| 11 May 2026 | 1 | 201000010913 | Corrective |
| 22 Feb 2026 | 1 | 201000028512 | Corrective |
| 14 Feb 2026 | 1 | 201000001410 | Corrective |
| 12 Feb 2026 | 1 | 206000018451 | Other maintenance |
| 26 Jan 2026 | 1 | 201000027275 | Corrective |
| 25 Jan 2026 | 1 | 205000035334 | Other maintenance |
| 13 Jan 2026 | 2 | 201000012088 | Corrective |
| 28 Dec 2025 | 1 | 203000006078 | Turnaround |
| 03 Dec 2025 | 1 | 201000013756 | Corrective |
| 11 Nov 2025 | 1 | 201000024097 | Corrective |
| 08 Nov 2025 | 1 | 203000004034 | Turnaround |