BEARING,ROLLER,CYL,1ROW,7215BDB
Material 4100000404 · BEARING · Plant 1000
ALong-leadMaintainHealthy
- Material
- 4100000404
- Category
- BEARING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (10 of 15 FuncLocs A/B)
- Supplier
- CAHAYA TEKNIK PERSADA PT
- Lead time
- 76 d · P80 97 d
- Unit price
- Rp 1.1M
Recommendation
- 1.Forecast 13 EA/year: 12 unplanned (recency-weighted compound poisson (own history)) + 1.4 from the maintenance plan.
- 2.Lead time ~76 days; expected demand during lead time 2.4.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 23.
- 4.Long lead time: 80% of deliveries took up to 97 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 15 FuncLoc(s), 10 of them criticality A/B.
- 6.ML early warning: 73% probability of demand in the next 90 days.
Long-leadML early warningSingle sourceOpen PO
On hand / on order
14 / 3
next delivery 02 Oct 2026
Today Min / Max
6 / 14
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 8
Rec. Max
23
order qty 13
Service level
100.0%
stockout risk now 0%
Unit price
Rp 1.1M
PO history
ML early warning: 73% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 15 days ago, 6 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1 units) excluded from the baseline.
Demand pattern Intermittent · 14 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.
Installed on 15 functional locations
10 with criticality A/B · 19 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-137A C4 PRODUCT COMPRESSOR | A | 1 | 2 | 1.43 |
| PX_PP-1634A QUENCH OIL PUMP | A | 1 | 1 | 0.19 |
| PY_KC-636C SLOP OIL COMPRESSOR | A | 1 | 1 | 0.57 |
| PX_KC-250D PROPYLENE FAN | A | 1 | 0 | 0.57 |
| PX_KT-308B TURBINE FOR KC-308B | A | 1 | 0 | 1.10 |
| PX_PP-583B WASH WATER PUMP | A | 1 | 0 | 0.19 |
| PX_KC-225D INHIBITOR COMPRESSOR | B | 1 | 9 | 2.71 |
| PX_PP-821 FEED PUMP | B | 2 | 2 | 0.62 |
| PX_PP-682A RECYCLE ETHANE PUMP | B | 1 | 1 | 0.62 |
| PX_PP-577-M MOTOR FOR PP-577 | B | 4 | 0 | 0.19 |
| PX_PP-1678A-M MOTOR FOR PP-1678A | C | 1 | 0 | 0.19 |
| PX_KT-447 TURBINE FOR KC-447 | S | 1 | 13 | 6.24 |
Lead time and procurement
Lead time 76 ± 42 days (PO history, 11 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 23 Jun 2026 | PR03 Regular replenishment | 5 | Rp 1.1M | 07 Sept 2026 | 76 d |
| 28 Apr 2026 | PR03 Regular replenishment | 6 | Rp 1.1M | 24 Jun 2026 | 57 d |
| 24 Apr 2026 | PR03 Regular replenishment | 4 | Rp 1.2M | 14 Jun 2026 | 51 d |
| 29 Mar 2026 | PR01 Import / long-lead | 3 | Rp 1.2M | 02 Oct 2026 open | 187 d |
| 16 Mar 2026 | PR03 Regular replenishment | 7 | Rp 1.1M | 07 Apr 2026 | 22 d |
| 12 Mar 2026 | PR06 Regular replenishment | 8 | Rp 1.1M | 10 May 2026 | 59 d |
| 06 Feb 2026 | PR03 Regular replenishment | 3 | Rp 1.1M | 15 Apr 2026 | 68 d |
| 28 Nov 2025 | PR01 Import / long-lead | 5 | Rp 1.2M | 03 Mar 2026 | 95 d |
| 01 Sept 2025 | PR04 Regular (other) | 4 | Rp 1.1M | 07 Dec 2025 | 97 d |
| 30 Jun 2025 | PR03 Regular replenishment | 6 | Rp 1.1M | 22 Sept 2025 | 84 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Jul 2027 | PX_PP-821 | Pump overhaul | 1.43 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 16 Sept 2026 | Medium | PX_KC-891A | KC-891A high vibration |
| 11 Sept 2026 | Low | PX_KC-225D | KC-225D lube oil filter DP high |
| 01 Sept 2026 | Low | PX_KT-447 | Replace lamp as per PM finding |
| 22 Aug 2026 | Low | PX_KC-225D | Install scaffolding at KC-225D |
| 27 Jul 2026 | Low | PX_KC-225D | Painting KC-225D |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 08 Jul 2026 | Medium | PX_KT-447 | Replace lamp as per PM finding |
| 06 Jul 2026 | Medium | PX_PP-821 | Replace bearing PP-821 |
| 20 Jun 2026 | Medium | PX_KC-225D | Inspect coupling KC-225D |
| 07 Jun 2026 | High | PX_KC-225D | KC-225D high vibration |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 16 Sept 2026 | 1 | 201000001079 | Corrective |
| 14 Aug 2026 | 1 | 201000026035 | Corrective |
| 30 Jun 2026 | 1 | 201000006253 | Corrective |
| 22 Jun 2026 | 1 | 201000031741 | Corrective |
| 28 Feb 2026 | 1 | 201000013980 | Corrective |
| 28 Feb 2026 | 1 | 201000038413 | Corrective |
| 19 Jan 2026 | 1 | 201000036088 | Corrective |
| 25 Dec 2025 | 1 | 201000024112 | Corrective |
| 18 Dec 2025 | 1 | 201000037525 | Corrective |
| 10 Dec 2025 | 1 | 201000037297 | Corrective |
| 25 Sept 2025 | 1 | 201000005798 | Corrective |
| 30 Aug 2025 | 3 | 201000023581 | Corrective |
| 24 Aug 2025 | 1 | 203000020904 | Turnaround |
| 31 Jul 2025 | 1 | 209000022794 | Other maintenance |
| 10 Jul 2025 | 1 | 209000008579 | Other maintenance |