BEARING,BALL,1ROW,DEEP GROOVE,6312
Material 4100000410 · BEARING · Plant 1000
AMonitorHealthy
- Material
- 4100000410
- Category
- BEARING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (11 of 16 FuncLocs A/B)
- Supplier
- GEMILANG MANDIRI JAYA PT
- Lead time
- 41 d · P80 44 d
- Unit price
- Rp 495,871
Recommendation
- 1.Forecast 13 EA/year: 13 unplanned (recency-weighted compound poisson (own history)).
- 2.Lead time ~41 days; expected demand during lead time 1.5.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 22.
- 4.Installed on 16 FuncLoc(s), 11 of them criticality A/B.
- 5.ML early warning: 83% probability of demand in the next 90 days.
ML early warningLast turnaround used 6Single sourceOpen PO
On hand / on order
3 / 7
next delivery 17 Oct 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 7
Rec. Max
22
order qty 14
Service level
99.9%
stockout risk now 0%
Unit price
Rp 495,871
PO history
ML early warning: 83% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 4 issue days in the last 180 days, last issue 11 days ago, 6 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (9 units) excluded from the baseline.
Demand pattern Lumpy · 13 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.
Installed on 16 functional locations
11 with criticality A/B · 24 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-867D CONDENSATE FAN | A | 1 | 6 | 2.71 |
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_KC-426D RICH AMINE BLOWER | A | 3 | 0 | 0.57 |
| PX_PP-1177C-M MOTOR FOR PP-1177C | A | 4 | 0 | 0.19 |
| PX_PP-1383 PROPYLENE PUMP | A | 1 | 0 | 0.19 |
| PX_PP-1865A METHANOL PUMP | A | 1 | 0 | 0.19 |
| PX_PP-882A-M MOTOR FOR PP-882A | A | 1 | 0 | 0.19 |
| PX_PP-891C CHARGE GAS PUMP | A | 1 | 0 | 0.19 |
| PX_PP-169A QUENCH OIL PUMP | B | 4 | 5 | 1.90 |
| PX_PP-1969B FEED PUMP | B | 1 | 0 | 0.19 |
| PX_PP-531B ETHYLENE PUMP | B | 1 | 0 | 0.19 |
| PX_PP-1115-M MOTOR FOR PP-1115 | C | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 41 ± 22 days (PO history, 5 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 04 Sept 2026 | PR03 Regular replenishment | 7 | Rp 506,138 | 17 Oct 2026 open | 43 d |
| 20 Apr 2026 | PR06 Regular replenishment | 11 | Rp 473,165 | 11 May 2026 | 21 d |
| 27 Sept 2025 | PR03 Regular replenishment | 5 | Rp 495,871 | 13 Nov 2025 | 47 d |
| 21 Jul 2025 | PR03 Regular replenishment | 14 | Rp 510,231 | 15 Aug 2025 | 25 d |
| 30 May 2025 | PR03 Regular replenishment | 12 | Rp 485,221 | 25 Jun 2025 | 26 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 17 Sept 2026 | Medium | PX_KC-867D | Leak from packing |
| 01 Sept 2026 | High | PX_KC-582B | KC-582B high vibration |
| 26 Aug 2026 | Low | PX_KC-582B | Painting KC-582B |
| 22 Jul 2026 | Medium | PX_PP-169A | Install cover plate for MCP cracking |
| 15 Jul 2026 | Medium | PX_KT-624A | [MSI-B-26-RXR-331/M] Replace line |
| 11 Jul 2026 | Medium | PX_KC-867D | KC-867D bearing temp high |
| 08 Jul 2026 | Low | PX_KC-582B | Install scaffolding at KC-582B |
| 25 Jun 2026 | Medium | PX_PP-169A | PP-169A seal leak |
| 03 Jun 2026 | Low | PX_KC-867D | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 20 Sept 2026 | 2 | 201000020402 | Corrective |
| 25 Jul 2026 | 1 | 203000004330 | Turnaround |
| 13 Jul 2026 | 1 | 201000024244 | Corrective |
| 30 Jun 2026 | 1 | 201000031423 | Corrective |
| 07 Apr 2026 | 1 | 201000023642 | Corrective |
| 08 Feb 2026 | 1 | 203000018609 | Turnaround |
| 25 Jan 2026 | 2 | 204000016196 | Preventive |
| 18 Jan 2026 | 2 | 201000023909 | Corrective |
| 11 Jan 2026 | 2 | 201000025650 | Corrective |
| 28 Dec 2025 | 1 | 201000031912 | Corrective |
| 04 Dec 2025 | 1 | 201000032016 | Corrective |
| 30 Nov 2025 | 1 | 203000009623 | Turnaround |
| 30 Nov 2025 | 1 | 203000012255 | Turnaround |
| 19 Nov 2025 | 2 | 203000038363 | Turnaround |
| 15 Nov 2025 | 1 | 203000023445 | Turnaround |