BEARING,BALL,1ROW,DEEP GROOVE,6214BDB

Material 4100000437 · BEARING · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100000437
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (8 of 9 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
44 d · P80 127 d
Unit price
Rp 507,462

Recommendation

  • 1.Forecast 7.1 EA/year: 6.3 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~44 days; expected demand during lead time 0.8.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 14.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 14 now.
  • 5.Long lead time: 80% of deliveries took up to 127 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 9 FuncLoc(s), 8 of them criticality A/B.
  • 7.ML early warning: 59% probability of demand in the next 90 days.
Proposed purchase requisition
14 EA
Rp 7.1M · order by 01 Oct 2026
Expected arrival ≈ 44 days
Long-leadML early warningLast turnaround used 1Single source
On hand / on order
0 / 0
no open PO
Today Min / Max
4 / 7
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
14
order qty 8
Service level
100.0%
stockout risk now 41%
Unit price
Rp 507,462
PO history
ML early warning: 59% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 84 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern Intermittent · 7 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 9 functional locations

8 with criticality A/B · 12 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_KT-460B
TURBINE FOR KC-460B
A121.96
PX_PP-912-M
MOTOR FOR PP-912
A410.19
PX_KC-620A
DEMIN WATER AIR COMPRESSOR
B121.00
PX_PP-958B
SEAL OIL PUMP
B120.62
PX_PP-210A
HYDROGEN PUMP
B110.19
PX_PP-1663B-M
MOTOR FOR PP-1663B
B100.19
PX_PP-319B
ETHYLENE PUMP
B100.19
PX_PP-1807C-M
MOTOR FOR PP-1807C
S100.19

Lead time and procurement

Lead time 44 ± 40 days (PO history + category, 2 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
14 Feb 2026PR03
Regular replenishment
5Rp 521,02920 Mar 202634 d
11 Nov 2025PR06
Regular replenishment
5Rp 493,89530 Nov 202519 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Aug 2027PX_KC-620ACompressor major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
22 Aug 2026MediumPX_PP-958BPP-958B discharge pressure low
26 May 2026LowPX_KT-397AFollow up after steam upset KT-397A
16 May 2026MediumPX_KT-397AReplace lamp as per PM finding
14 May 2026LowPX_KT-397AKT-397A trip test
02 Apr 2026MediumPX_KT-397AFollow up after steam upset KT-397A
15 Dec 2025MediumPX_KC-620AInspect coupling KC-620A
12 Dec 2025LowPX_KT-460BKT-460B governor valve hunting
27 Jul 2025MediumPX_KT-460BFollow up after steam upset KT-460B
21 May 2025MediumPX_PP-958BInstall scaffolding at PP-958B
14 May 2025LowPX_PP-912-MInstall scaffolding at PP-912-M

Recent goods issues

Posting dateQtyOrderOrder type
09 Jul 20262209000012005Other maintenance
12 Jun 20263201000023717Corrective
29 Jan 20261201000011859Corrective
24 Jan 20261201000003273Corrective
11 Dec 20251201000018729Corrective
10 Nov 20251203000023445Turnaround
05 Oct 20251201000006219Corrective
15 Sept 20251201000012551Corrective