BEARING,ROLLER,CYL,1ROW,6319

Material 4100000532 · BEARING · Plant 1000

ALong-leadReorderNormalSlow-moving
Material
4100000532
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 7 FuncLocs A/B)
Supplier
MITRA PERKASA NUSANTARA PT
Lead time
66 d · P80 127 d
Unit price
Rp 2.5M

Recommendation

  • 1.Forecast 4.0 EA/year: 3.3 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~66 days; expected demand during lead time 0.6.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 10.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 8 now.
  • 5.Long lead time: 80% of deliveries took up to 127 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 7 FuncLoc(s), 4 of them criticality A/B.
  • 7.ML early warning: 35% probability of demand in the next 90 days.
Proposed purchase requisition
8 EA
Rp 20.3M · order by 01 Oct 2026
Expected arrival ≈ 66 days
Long-leadML early warningLast turnaround used 1Single source
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
10
order qty 5
Service level
100.0%
stockout risk now 9%
Unit price
Rp 2.5M
PO history
ML early warning: 35% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 200 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 7 functional locations

4 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_PP-106B-M
MOTOR FOR PP-106B
A120.62
PX_PP-387
INHIBITOR PUMP
A110.62
PX_PP-1007C-M
MOTOR FOR PP-1007C
B100.19
PX_PP-643A-M
MOTOR FOR PP-643A
B100.19
PX_PP-536
HYDROGEN PUMP
C100.19
PX_KC-890A
INHIBITOR FAN
S121.00
PX_PP-1906B
LUBE OIL PUMP
S100.19

Lead time and procurement

Lead time 66 ± 40 days (PO history + category, 2 PO lines) · on-time 48%

PR dateTypeQtyUnit priceDeliveryLead time
06 Jul 2026PR03
Regular replenishment
4Rp 2.6M14 Sept 202670 d
07 Oct 2025PR03
Regular replenishment
4Rp 2.5M09 Jan 202694 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Aug 2027PX_PP-536Pump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
29 Jun 2026MediumPY_PP-106B-MMegger test PP-106B-M
03 Oct 2025MediumPX_KC-890ALeak from packing
11 Jun 2025MediumPX_PP-387PP-387 seal leak
17 May 2025LowPX_KC-890AReplace lamp as per PM finding
11 May 2025MediumPY_PP-106B-MLeak from packing

Recent goods issues

Posting dateQtyOrderOrder type
15 Mar 20261204000017829Preventive
21 Feb 20262201000006434Corrective
02 Jan 20261201000034812Corrective
31 Dec 20251201000008562Corrective
27 Dec 20251201000030309Corrective
18 Dec 20251203000033807Turnaround
08 Dec 20251201000037522Corrective
22 Oct 20251201000027084Corrective