BEARING,ROLLER,CYL,1ROW,6319
Material 4100000532 · BEARING · Plant 1000
ALong-leadReorderNormalSlow-moving
- Material
- 4100000532
- Category
- BEARING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 7 FuncLocs A/B)
- Supplier
- MITRA PERKASA NUSANTARA PT
- Lead time
- 66 d · P80 127 d
- Unit price
- Rp 2.5M
Recommendation
- 1.Forecast 4.0 EA/year: 3.3 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
- 2.Lead time ~66 days; expected demand during lead time 0.6.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 10.
- 4.On hand 2 + on order 0 is at or below the reorder point: order 8 now.
- 5.Long lead time: 80% of deliveries took up to 127 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 7 FuncLoc(s), 4 of them criticality A/B.
- 7.ML early warning: 35% probability of demand in the next 90 days.
Proposed purchase requisition
8 EA
Rp 20.3M · order by 01 Oct 2026
Expected arrival ≈ 66 days
Long-leadML early warningLast turnaround used 1Single source
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
10
order qty 5
Service level
100.0%
stockout risk now 9%
Unit price
Rp 2.5M
PO history
ML early warning: 35% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 200 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1 units) excluded from the baseline.
Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.
Installed on 7 functional locations
4 with criticality A/B · 7 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PY_PP-106B-M MOTOR FOR PP-106B | A | 1 | 2 | 0.62 |
| PX_PP-387 INHIBITOR PUMP | A | 1 | 1 | 0.62 |
| PX_PP-1007C-M MOTOR FOR PP-1007C | B | 1 | 0 | 0.19 |
| PX_PP-643A-M MOTOR FOR PP-643A | B | 1 | 0 | 0.19 |
| PX_PP-536 HYDROGEN PUMP | C | 1 | 0 | 0.19 |
| PX_KC-890A INHIBITOR FAN | S | 1 | 2 | 1.00 |
| PX_PP-1906B LUBE OIL PUMP | S | 1 | 0 | 0.19 |
Lead time and procurement
Lead time 66 ± 40 days (PO history + category, 2 PO lines) · on-time 48%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 06 Jul 2026 | PR03 Regular replenishment | 4 | Rp 2.6M | 14 Sept 2026 | 70 d |
| 07 Oct 2025 | PR03 Regular replenishment | 4 | Rp 2.5M | 09 Jan 2026 | 94 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 02 Aug 2027 | PX_PP-536 | Pump overhaul | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 29 Jun 2026 | Medium | PY_PP-106B-M | Megger test PP-106B-M |
| 03 Oct 2025 | Medium | PX_KC-890A | Leak from packing |
| 11 Jun 2025 | Medium | PX_PP-387 | PP-387 seal leak |
| 17 May 2025 | Low | PX_KC-890A | Replace lamp as per PM finding |
| 11 May 2025 | Medium | PY_PP-106B-M | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 15 Mar 2026 | 1 | 204000017829 | Preventive |
| 21 Feb 2026 | 2 | 201000006434 | Corrective |
| 02 Jan 2026 | 1 | 201000034812 | Corrective |
| 31 Dec 2025 | 1 | 201000008562 | Corrective |
| 27 Dec 2025 | 1 | 201000030309 | Corrective |
| 18 Dec 2025 | 1 | 203000033807 | Turnaround |
| 08 Dec 2025 | 1 | 201000037522 | Corrective |
| 22 Oct 2025 | 1 | 201000027084 | Corrective |