BEARING,BALL,1ROW,DEEP GROOVE,6207-2Z

Material 4100000571 · BEARING · Plant 1000

AMonitorHealthy
Material
4100000571
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 4 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
50 d · P80 59 d
Unit price
Rp 1.2M

Recommendation

  • 1.Forecast 5.8 EA/year: 5.0 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~50 days; expected demand during lead time 0.7.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 10.
  • 4.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
  • 5.ML early warning: 79% probability of demand in the next 90 days.
ML early warningLast turnaround used 1Single sourceOpen PO
On hand / on order
4 / 3
next delivery 25 Oct 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
10
order qty 6
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.2M
PO history
ML early warning: 79% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 10 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 5 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern Lumpy · 7 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 4 functional locations

1 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_KC-636C
SLOP OIL COMPRESSOR
A110.57
PX_PP-1744
PROPYLENE PUMP
C100.19
PX_KT-778A
TURBINE FOR KC-778A
S101.10
PX_KT-875
TURBINE FOR KC-875
S101.10

Lead time and procurement

Lead time 50 ± 33 days (PO history, 9 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
20 Aug 2026PR03
Regular replenishment
3Rp 1.3M25 Oct 2026
open
66 d
08 Aug 2026PR03
Regular replenishment
3Rp 1.2M08 Sept 202631 d
21 Jul 2026PR03
Regular replenishment
2Rp 1.2M08 Aug 202618 d
01 Jul 2026PR06
Regular replenishment
2Rp 1.3M04 Aug 202634 d
06 May 2026PR03
Regular replenishment
4Rp 1.2M04 Jun 202629 d
24 Dec 2025PR03
Regular replenishment
4Rp 1.2M30 Jan 202637 d
19 Jul 2025PR05
Project / turnaround
4Rp 1.2M29 Aug 202541 d
31 May 2025PR05
Project / turnaround
5Rp 1.2M28 Sept 2025120 d
31 May 2025PR03
Regular replenishment
3Rp 1.2M25 Jul 202555 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
02 Mar 2027PX_PP-1744Pump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 May 2025MediumPY_KC-636CInstall scaffolding at KC-636C

Recent goods issues

Posting dateQtyOrderOrder type
21 Sept 20261201000013925Corrective
10 Aug 20261201000002413Corrective
13 Jul 20261201000000855Corrective
24 Feb 20261201000036183Corrective
10 Feb 20263204000029556Preventive
29 Jan 20261203000033471Turnaround
07 Jan 20261201000020180Corrective
21 Oct 20251201000010832Corrective
18 Jul 20251209000039143Other maintenance