BEARING,ROLLER,CYL,1ROW,6313

Material 4100000576 · BEARING · Plant 1000

AReorderNormalBelow reorder point
Material
4100000576
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (6 of 11 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
57 d · P80 77 d
Unit price
Rp 2.0M

Recommendation

  • 1.Forecast 3.6 EA/year: 2.9 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~57 days; expected demand during lead time 0.5.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 8.
  • 4.On hand 1 + on order 0 is at or below the reorder point: order 7 now.
  • 5.Installed on 11 FuncLoc(s), 6 of them criticality A/B.
  • 6.ML early warning: 43% probability of demand in the next 90 days.
Proposed purchase requisition
7 EA
Rp 14.1M · order by 01 Oct 2026
Expected arrival ≈ 57 days
ML early warningSingle source
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
8
order qty 4
Service level
100.0%
stockout risk now 8%
Unit price
Rp 2.0M
PO history
ML early warning: 43% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 89 days ago, 0 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.4B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 11 functional locations

6 with criticality A/B · 14 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-527
METHANOL BLOWER
A100.57
PX_PP-1604A
DILUTION STEAM PUMP
A100.19
PX_PP-248B
RICH AMINE PUMP
A300.19
PX_PP-390B-M
MOTOR FOR PP-390B
A100.19
PX_PP-1253B
LUBE OIL PUMP
B120.62
PX_PP-1448B
ETHYLENE PUMP
B110.62
PX_KT-264A
TURBINE FOR KC-264A
S142.39
PX_KC-856A
DEMIN WATER COMPRESSOR
S221.00
PX_KC-890A
INHIBITOR FAN
S121.00
PX_KC-236B
DILUTION STEAM FAN
S110.57
PX_KT-778A
TURBINE FOR KC-778A
S101.10

Lead time and procurement

Lead time 57 ± 35 days (PO history, 4 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
04 May 2026PR03
Regular replenishment
2Rp 2.0M04 Jul 202661 d
09 Nov 2025PR03
Regular replenishment
2Rp 1.9M18 Feb 2026101 d
03 Nov 2025PR03
Regular replenishment
1Rp 2.0M07 Dec 202534 d
18 Jun 2025PR03
Regular replenishment
1Rp 2.1M28 Jul 202540 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
14 Jul 2026LowPX_KC-856AInstall scaffolding at KC-856A
11 Jun 2026LowPX_KT-264ALeak from packing
21 Apr 2026LowPX_KT-264AFollow up after steam upset KT-264A
25 Mar 2026MediumPX_PP-1253BPP-1253B seal leak
21 Oct 2025MediumPX_KT-264AKT-264A governor valve hunting
03 Oct 2025MediumPX_KC-890ALeak from packing
09 Aug 2025MediumPX_KC-856AReplace lamp as per PM finding
21 Jun 2025MediumPX_PP-1448BPP-1448B abnormal noise
31 May 2025MediumPX_KT-264AInstall scaffolding at KT-264A
17 May 2025LowPX_KC-890AReplace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
04 Jul 20261201000014145Corrective
06 Mar 20261201000036940Corrective
26 Oct 20251201000017078Corrective
19 Jul 20251203000031669Turnaround
12 Jun 20251201000002498Corrective