Sparely
DU

BEARING,BALL,1ROW,DEEP GROOVE,7216

Material 4100000725 · BEARING · Plant 1000

AReorderNormalBelow reorder point
Material
4100000725
Category
BEARING
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 1.4M (est.)

Recommendation

  • 1.Forecast 4.7 EA/year: 4.0 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 2.Lead time ~55 days; expected demand during lead time 0.6.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 10.
  • 4.On hand 4 + on order 0 is at or below the reorder point: order 6 now.
  • 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
6 EA
Rp 8.5M · order by 01 Oct 2026
Expected arrival ≈ 55 days
Convert to Stock ItemLast turnaround used 2Price estimatedLead time estimated
On hand / on order
4 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
10
order qty 5
Service level
99.9%
stockout risk now 1%
Unit price
Rp 1.4M
Category + unit estimate
ML early warning: 30% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 48 days ago, 2 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (3 units) excluded from the baseline.

Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 3 functional locations

2 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-447
LUBE OIL COMPRESSOR
A141.85
PX_KC-391D
QUENCH WATER COMPRESSOR
A121.43
PX_KT-264A
TURBINE FOR KC-264A
S142.39

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
26 Dec 2026PX_KT-264ATurbine major overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
17 Aug 2026MediumPX_KC-447Leak from packing
07 Jul 2026MediumPX_KC-447Replace lamp as per PM finding
11 Jun 2026LowPX_KT-264ALeak from packing
21 Apr 2026LowPX_KT-264AFollow up after steam upset KT-264A
27 Dec 2025LowPX_KC-391DLeak from packing
21 Oct 2025MediumPX_KT-264AKT-264A governor valve hunting
07 Sept 2025MediumPX_KC-447Replace lamp as per PM finding
18 Jul 2025HighPX_KC-391DKC-391D high vibration
31 May 2025MediumPX_KT-264AInstall scaffolding at KT-264A
18 May 2025MediumPX_KC-447Replace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
14 Aug 20261201000012683Corrective
28 Jan 20261203000033471Turnaround
27 Dec 20251201000019016Corrective
22 Dec 20251203000035272Turnaround
07 Dec 20252201000024118Corrective
30 Aug 20251203000006603Turnaround
27 Aug 20252201000009099Corrective