Sparely
DU

BEARING,BALL,ANGULAR,6317

Material 4100000756 · BEARING · Plant 1000

AMaintainHealthy
Material
4100000756
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (3 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 1.4M (est.)

Recommendation

  • 1.Forecast 4.8 EA/year: 4.8 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~55 days; expected demand during lead time 0.7.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 10.
  • 4.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
  • 5.ML early warning: 43% probability of demand in the next 90 days.
ML early warningPrice estimatedLead time estimated
On hand / on order
8 / 0
no open PO
Today Min / Max
2 / 4
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
10
order qty 5
Service level
100.0%
stockout risk now 0%
Unit price
Rp 1.4M
Category + unit estimate
ML early warning: 43% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 70 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 7 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 5 functional locations

3 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-244A-M
MOTOR FOR PP-244A
A131.47
PX_KC-618B
WASH WATER BLOWER
A100.57
PX_KT-308B
TURBINE FOR KC-308B
A101.10
PX_KT-447
TURBINE FOR KC-447
S1136.24
PX_KT-875
TURBINE FOR KC-875
S101.10

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Sept 2026LowPX_KT-447Replace lamp as per PM finding
08 Jul 2026MediumPX_KT-447Replace lamp as per PM finding
25 May 2026LowPX_PP-244A-MPP-244A-M bearing noise
13 May 2026LowPX_KT-447KT-447 trip test
19 Apr 2026LowPX_KT-447Follow up after steam upset KT-447
30 Mar 2026LowPX_KT-447Leak from packing
28 Mar 2026MediumPX_KT-447Follow up after steam upset KT-447
14 Mar 2026MediumPX_KT-447KT-447 steam leak at gland
14 Jan 2026MediumPX_KT-447Follow up after steam upset KT-447
21 Nov 2025MediumPX_KT-447Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
23 Jul 20261201000027503Corrective
09 Mar 20261201000025379Corrective
31 Dec 20251201000013760Corrective
02 Dec 20251201000006865Corrective
30 Oct 20251209000022917Other maintenance
14 Jul 20251209000039143Other maintenance
14 Jun 20252201000013381Corrective