Sparely
DU

BEARING,ROLLER,CYL,1ROW,6305-2Z

Material 4100000783 · BEARING · Plant 1000

ALong-leadReorderNormalBelow reorder point
Material
4100000783
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 4 FuncLocs A/B)
Supplier
DUTA ENERGI ABADI PT
Lead time
108 d · P80 183 d
Unit price
Rp 1.8M

Recommendation

  • 1.Forecast 9.0 EA/year: 9.0 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~108 days; expected demand during lead time 2.7.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 21.
  • 4.On hand 9 + on order 3 is at or below the reorder point: order 9 now.
  • 5.Long lead time: 80% of deliveries took up to 183 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
  • 7.ML early warning: 55% probability of demand in the next 90 days.
Proposed purchase requisition
9 EA
Rp 15.8M · order by 01 Oct 2026
Expected arrival ≈ 108 days
Long-leadML early warningLast turnaround used 4Single sourceOpen PO
On hand / on order
9 / 3
next delivery 03 Sept 2027
Today Min / Max
3 / 5
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 10
Rec. Max
21
order qty 9
Service level
100.0%
stockout risk now 0%
Unit price
Rp 1.8M
PO history
ML early warning: 55% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 74 days ago, 8 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (6 units) excluded from the baseline.

Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 4 functional locations

1 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1384B
COOLING WATER PUMP
A100.19
PX_PP-408B-M
MOTOR FOR PP-408B
C121.05
PX_KC-843
FUEL OIL COMPRESSOR
S1218.28
PX_KT-202
TURBINE FOR KC-202
S142.81

Lead time and procurement

Lead time 108 ± 43 days (PO history, 4 PO lines) · on-time 42%

PR dateTypeQtyUnit priceDeliveryLead time
08 Jul 2026PR01
Import / long-lead
3Rp 1.7M03 Sept 2027
open
422 d
13 Mar 2026PR03
Regular replenishment
6Rp 1.8M22 Sept 2026193 d
05 Feb 2026PR03
Regular replenishment
4Rp 1.8M09 May 202693 d
13 Nov 2025PR06
Regular replenishment
5Rp 1.8M09 May 2026177 d
16 May 2025PR03
Regular replenishment
6Rp 1.7M24 Sept 2025131 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
21 Sept 2026MediumPX_KC-843Painting KC-843
18 Sept 2026MediumPX_KT-202Repair insulation KT-202
16 Sept 2026LowPX_KC-843Inspect coupling KC-843
29 Aug 2026MediumPX_KC-843Replace lamp as per PM finding
26 Aug 2026MediumPX_KC-843[MSI-B-26-RLH-211] Permanent repair
14 Aug 2026MediumPX_KC-843KC-843 lube oil filter DP high
06 Aug 2026MediumPX_KC-843Replace lamp as per PM finding
02 Aug 2026EmergencyPX_KC-843[MSI-B-26-KRX-321] Permanent repair
14 Jul 2026MediumPX_KC-843KC-843 bearing temp high
09 Jun 2026LowPX_KC-843Overhaul

Recent goods issues

Posting dateQtyOrderOrder type
19 Jul 20263201000028005Corrective
23 Jun 20262201000023783Corrective
15 Jan 20261201000030946Corrective
31 Dec 20252201000020705Corrective
28 Dec 20252203000016277Turnaround
01 Nov 20252203000039255Turnaround
19 Sept 20251201000013763Corrective
27 Aug 20252203000006603Turnaround
11 Aug 20253201000005686Corrective