BEARING,ROLLER,CYL,1ROW,6212

Material 4100000856 · BEARING · Plant 1000

AMaintainHealthy
Material
4100000856
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 5 FuncLocs A/B)
Supplier
CAHAYA TEKNIK PERSADA PT
Lead time
52 d · P80 57 d
Unit price
Rp 2.3M

Recommendation

  • 1.Forecast 3.4 EA/year: 3.4 unplanned (recency-weighted compound poisson (own history)).
  • 2.Lead time ~52 days; expected demand during lead time 0.5.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 8.
  • 4.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
  • 5.ML early warning: 60% probability of demand in the next 90 days.
ML early warningSingle source
On hand / on order
7 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
8
order qty 4
Service level
100.0%
stockout risk now 0%
Unit price
Rp 2.3M
PO history
ML early warning: 60% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 111 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 2 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 5 functional locations

4 with criticality A/B · 8 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_PP-1862
HYDROGEN PUMP
A151.47
PX_PP-1194
FEED PUMP
A421.05
PX_PP-1939-M
MOTOR FOR PP-1939
A100.19
PY_PP-203B
DEMIN WATER PUMP
S172.76

Lead time and procurement

Lead time 52 ± 23 days (PO history, 4 PO lines) · on-time 36%

PR dateTypeQtyUnit priceDeliveryLead time
05 Aug 2026PR06
Regular replenishment
1Rp 2.4M15 Sept 202641 d
02 Jul 2026PR03
Regular replenishment
3Rp 2.3M25 Aug 202654 d
16 Jan 2026PR03
Regular replenishment
2Rp 2.4M24 Feb 202639 d
27 Sept 2025PR03
Regular replenishment
1Rp 2.3M28 Nov 202562 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
17 Aug 2026MediumPY_PP-203BOverhaul PP-203B
14 Aug 2026MediumPY_PP-203BPP-203B high vibration
09 Jul 2026MediumPY_PP-203BPainting PP-203B
31 May 2026LowPX_PP-1862PP-1862 seal leak
26 May 2026LowPX_KT-397AFollow up after steam upset KT-397A
17 May 2026MediumPX_PP-1862Replace lamp as per PM finding
16 May 2026MediumPX_KT-397AReplace lamp as per PM finding
14 May 2026LowPX_KT-397AKT-397A trip test
10 Apr 2026HighPX_PP-1862Install scaffolding at PP-1862
02 Apr 2026MediumPX_KT-397AFollow up after steam upset KT-397A

Recent goods issues

Posting dateQtyOrderOrder type
12 Jun 20261201000031684Corrective
06 Mar 20261201000016359Corrective
02 Jan 20261201000017485Corrective
16 Dec 20251201000010670Corrective
22 May 20251201000030802Corrective
09 May 20251204000006617Preventive