BEARING,BALL,ANGULAR,6210BDB

Material 4100000874 · BEARING · Plant 1000

AReorderCriticalStockout
Material
4100000874
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 4 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 1.4M (est.)

Recommendation

  • 1.Forecast 5.0 EA/year: 5.0 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~55 days; expected demand during lead time 0.8.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 12.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 12 now.
  • 5.Installed on 4 FuncLoc(s), 4 of them criticality A/B.
  • 6.ML early warning: 35% probability of demand in the next 90 days.
Proposed purchase requisition
12 EA
Rp 17.1M · order by 01 Oct 2026
Expected arrival ≈ 55 days
ML early warningLast turnaround used 2Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
12
order qty 6
Service level
100.0%
stockout risk now 40%
Unit price
Rp 1.4M
Category + unit estimate
ML early warning: 35% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 14 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (2 units) excluded from the baseline.

Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 4 functional locations

4 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1766A
ETHYLENE PUMP
A110.19
PX_PP-912
BOTTOM PUMP
B120.62
PX_PP-1969B
FEED PUMP
B100.19
PX_PP-657C
SEAL OIL PUMP
B100.19

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
16 Jul 2026MediumPX_PP-912Replace bearing PP-912
20 May 2025MediumPX_PP-1766APSM25/Install cover plate for MCP cracki
03 May 2025MediumPX_PP-912PP-912 abnormal noise

Recent goods issues

Posting dateQtyOrderOrder type
17 Sept 20261201000028695Corrective
02 Aug 20261201000029979Corrective
25 Jul 20262201000024842Corrective
19 Feb 20262201000019173Corrective
28 Dec 20251203000036428Turnaround
08 Nov 20251203000039046Turnaround