Sparely
DU

BEARING,BALL,1ROW,DEEP GROOVE,7208BDB

Material 4100000924 · BEARING · Plant 1000

AReduceExcess
Material
4100000924
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (5 of 5 FuncLocs A/B)
Supplier
ANUGRAH INSTRUMEN SENTOSA PT
Lead time
43 d · P80 36 d
Unit price
Rp 1.4M

Recommendation

  • 1.Forecast 5.0 EA/year: 4.3 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
  • 2.Lead time ~43 days; expected demand during lead time 0.5.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 10.
  • 4.Stock 97 exceeds the level to keep (10) by 87.
  • 5.Installed on 5 FuncLoc(s), 5 of them criticality A/B.
  • 6.ML early warning: 55% probability of demand in the next 90 days.
ML early warningLast turnaround used 2Single source
On hand / on order
97 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
10
order qty 5
Service level
100.0%
stockout risk now 0%
Unit price
Rp 1.4M
PO history
ML early warning: 55% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 105 days ago, 2 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (2 units) excluded from the baseline.

Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.8B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 5 functional locations

5 with criticality A/B · 10 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-479C
DILUTION STEAM COMPRESSOR
A452.71
PX_KT-397A
TURBINE FOR KC-397A
A152.81
PX_PP-1369C-M
MOTOR FOR PP-1369C
B300.19
PX_PP-1370C
FUEL OIL PUMP
B100.19
PX_PP-1952C
CHARGE GAS PUMP
B100.19

Lead time and procurement

Lead time 43 ± 19 days (PO history, 4 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
10 Aug 2026PR03
Regular replenishment
4Rp 1.4M18 Sept 202639 d
11 Jan 2026PR05
Project / turnaround
3Rp 1.5M11 Feb 202631 d
12 Dec 2025PR03
Regular replenishment
2Rp 1.5M15 Jan 202634 d
28 Sept 2025PR03
Regular replenishment
4Rp 1.4M31 Oct 202533 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Dec 2026PX_PP-1952CPump overhaul0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
10 Sept 2026MediumPX_KC-479CKC-479C bearing temp high
18 Aug 2026LowPX_KC-479CLeak from packing
31 May 2026MediumPX_KC-479C[MSI-B-26-KNK-222/M] Replace line
26 May 2026LowPX_KT-397AFollow up after steam upset KT-397A
16 May 2026MediumPX_KT-397AReplace lamp as per PM finding
14 May 2026LowPX_KT-397AKT-397A trip test
02 Apr 2026MediumPX_KT-397AFollow up after steam upset KT-397A
23 Sept 2025LowPX_KC-479COverhaul
02 Jul 2025LowPX_KC-479CKC-479C bearing temp high
10 May 2025MediumPX_KT-397ALeak from packing

Recent goods issues

Posting dateQtyOrderOrder type
18 Jun 20261201000010724Corrective
25 Mar 20261201000000306Corrective
08 Mar 20261204000033725Preventive
24 Feb 20261201000009373Corrective
20 Jan 20262203000029956Turnaround
16 Dec 20252201000026400Corrective
29 Oct 20251201000029147Corrective
24 Oct 20251201000012287Corrective