BEARING,BALL,ANGULAR,7206-2Z
Material 4100000957 · BEARING · Plant 1000
AReorderNormalBelow reorder point
- Material
- 4100000957
- Category
- BEARING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 55 d · P80 127 d
- Unit price
- Rp 1.4M (est.)
Recommendation
- 1.Forecast 2.2 EA/year: 2.2 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~55 days; expected demand during lead time 0.3.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 4.On hand 1 + on order 0 is at or below the reorder point: order 5 now.
- 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
5 EA
Rp 7.1M · order by 01 Oct 2026
Expected arrival ≈ 55 days
Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
100.0%
stockout risk now 5%
Unit price
Rp 1.4M
Category + unit estimate
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 70 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.
Installed on 2 functional locations
2 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-717 FLUSHING OIL COMPRESSOR | A | 1 | 9 | 4.00 |
| PX_KT-419A TURBINE FOR KC-419A | A | 1 | 6 | 2.81 |
Lead time and procurement
Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 21 Sept 2026 | Low | PX_KC-717 | Leak from packing |
| 08 Aug 2026 | Medium | PX_KC-717 | Repair insulation KC-717 |
| 20 Jul 2026 | Low | PX_KC-717 | Inspect coupling KC-717 |
| 05 Jul 2026 | Medium | PX_KC-717 | Overhaul |
| 03 Apr 2026 | Medium | PX_KT-419A | KT-419A steam leak at gland |
| 17 Mar 2026 | Medium | PX_KT-419A | Install cover plate for MCP cracking |
| 12 Mar 2026 | Low | PX_KC-717 | Replace lamp as per PM finding |
| 01 Mar 2026 | Medium | PX_KC-717 | Leak from packing |
| 20 Nov 2025 | Medium | PX_KT-419A | Leak from packing |
| 15 Nov 2025 | Low | PX_KC-717 | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 23 Jul 2026 | 1 | 201000031020 | Corrective |
| 21 Jul 2025 | 1 | 201000030417 | Corrective |