BEARING,ROLLER,CYL,1ROW,6314-2Z

Material 4100001089 · BEARING · Plant 1000

AReorderNormalSlow-moving
Material
4100001089
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (4 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 1.4M (est.)

Recommendation

  • 1.Forecast 5.2 EA/year: 5.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~55 days; expected demand during lead time 0.8.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 12.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 10 now.
  • 5.Installed on 5 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
10 EA
Rp 14.2M · order by 01 Oct 2026
Expected arrival ≈ 55 days
Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
12
order qty 6
Service level
99.9%
stockout risk now 6%
Unit price
Rp 1.4M
Category + unit estimate
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 318 days ago, 4 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 5 functional locations

4 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-479C
DILUTION STEAM COMPRESSOR
A152.71
PX_PP-1862
HYDROGEN PUMP
A151.47
PX_KC-663A
CONDENSATE FAN
A110.57
PX_KC-563B
GASOLINE COMPRESSOR
B100.57
PX_KC-458D
SLOP OIL FAN
S193.14

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
19 Sept 2026MediumPX_KC-458DKC-458D lube oil filter DP high
16 Sept 2026LowPX_KC-458DKC-458D lube oil filter DP high
10 Sept 2026MediumPX_KC-479CKC-479C bearing temp high
18 Aug 2026LowPX_KC-479CLeak from packing
24 Jun 2026MediumPX_KC-458DKC-458D bearing temp high
31 May 2026MediumPX_KC-479C[MSI-B-26-KNK-222/M] Replace line
31 May 2026LowPX_PP-1862PP-1862 seal leak
17 May 2026MediumPX_PP-1862Replace lamp as per PM finding
10 Apr 2026HighPX_PP-1862Install scaffolding at PP-1862
15 Mar 2026MediumPX_KC-458DPainting KC-458D

Recent goods issues

Posting dateQtyOrderOrder type
17 Nov 20252201000036809Corrective