BEARING,ROLLER,CYL,1ROW,6311BDB

Material 4100001125 · BEARING · Plant 1000

AMaintainCritical insurance spare
Material
4100001125
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 1.4M (est.)

Recommendation

  • 1.Forecast 0.4 EA/year: 0.4 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~55 days; expected demand during lead time 0.1.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 4.No issue in 17 months, but it protects critical equipment: keep it.
  • 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
4 / 0
no open PO
Today Min / Max
4 / 6
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 1.4M
Category + unit estimate
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 148.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 3 functional locations

2 with criticality A/B · 6 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KC-247A
SLOP OIL FAN
A194.00
PX_KT-419A
TURBINE FOR KC-419A
A462.81
PX_KC-293B
C4 PRODUCT COMPRESSOR
S100.57

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
27 Aug 2026HighPX_KC-247AInspect coupling KC-247A
14 Jul 2026MediumPX_KC-247AReplace lamp as per PM finding
29 Jun 2026LowPX_KC-247AKC-247A high vibration
04 Jun 2026LowPX_KC-247AKC-247A bearing temp high
06 Apr 2026MediumPX_KC-247AKC-247A bearing temp high
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
20 Nov 2025MediumPX_KC-247AReplace lamp as per PM finding
20 Nov 2025MediumPX_KT-419ALeak from packing
10 Nov 2025MediumPX_KT-419APainting KT-419A

Recent goods issues

Never issued in the 17-month history.