BEARING,BALL,1ROW,DEEP GROOVE,6218
Material 4100001213 · BEARING · Plant 1000
ALong-leadMonitorInsurance gap
- Material
- 4100001213
- Category
- BEARING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- RAJAWALI TEKNIK PRATAMA PT
- Lead time
- 59 d · P80 127 d
- Unit price
- Rp 702,071
Recommendation
- 1.Forecast 0.2 EA/year: 0.2 unplanned (installed-base failure prior (no history)).
- 2.Lead time ~59 days; expected demand during lead time 0.0.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
- 4.Never issued in 17 months: review with reliability engineering before buying an insurance spare.
- 5.Long lead time: 80% of deliveries took up to 127 days and the fastest seen in its category 23 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Insurance spare candidateLong-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 19 Nov 2026
Today Min / Max
2 / 6
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 702,071
PO history
ML early warning: 29% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 66.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.
Installed on 2 functional locations
2 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KC-222B LEAN AMINE COMPRESSOR | A | 1 | 5 | 1.85 |
| PX_KC-284A WASH WATER COMPRESSOR | B | 1 | 2 | 1.43 |
Lead time and procurement
Lead time 59 ± 40 days (PO history + category, 2 PO lines) · on-time 41%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 11 Sept 2026 | PR03 Regular replenishment | 2 | Rp 701,766 | 19 Nov 2026 open | 69 d |
| 28 May 2025 | PR03 Regular replenishment | 2 | Rp 702,375 | 26 Jul 2025 | 59 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 02 Jul 2026 | High | PX_KC-222B | Replace lamp as per PM finding |
| 05 Feb 2026 | Medium | PX_KC-222B | Install scaffolding at KC-222B |
| 01 Jan 2026 | Low | PX_KC-222B | KC-222B high vibration |
| 16 Nov 2025 | Medium | PX_KC-222B | KC-222B lube oil filter DP high |
| 04 Sept 2025 | Medium | PX_KC-284A | KC-284A lube oil filter DP high |
| 08 Jul 2025 | Medium | PX_KC-284A | KC-284A high vibration |
| 17 May 2025 | Low | PX_KC-222B | Install scaffolding at KC-222B |
Recent goods issues
Never issued in the 17-month history.