Sparely
DU

BEARING,BALL,ANGULAR,NU315

Material 4100001251 · BEARING · Plant 1000

AReduceSlow-moving
Material
4100001251
Category
BEARING
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 5 FuncLocs A/B)
Supplier
No PO history
Lead time
55 d · P80 127 d
Unit price
Rp 1.4M (est.)

Recommendation

  • 1.Forecast 0.8 EA/year: 0.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~55 days; expected demand during lead time 0.1.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 5 exceeds the level to keep (3) by 2.
  • 5.Installed on 5 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
5 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
100.0%
stockout risk now 0%
Unit price
Rp 1.4M
Category + unit estimate
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 246 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 403.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~23 days.

Installed on 5 functional locations

1 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PP-1049
PROPYLENE PUMP
A100.19
PX_PP-1194B-M
MOTOR FOR PP-1194B
C100.19
PX_KC-984C
CONDENSATE COMPRESSOR
S121.00
PX_KC-293B
C4 PRODUCT COMPRESSOR
S100.57
PX_PP-705
METHANOL PUMP
S100.19

Lead time and procurement

Lead time 55 ± 40 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
05 Sept 2025MediumPX_KC-984COverhaul
30 May 2025LowPX_KC-984CInspect coupling KC-984C

Recent goods issues

Posting dateQtyOrderOrder type
28 Jan 20261201000036610Corrective